Building an ADU in Sunnyvale

City code and California law · Last reviewed October 9, 2026

Sunnyvale allows up to three ADUs with a single-family home: one new construction ADU, one conversion ADU and one junior ADU (but not both a conversion inside the house and an attached addition). A new ADU can be up to 1,000 sq ft. Most ADUs, including any new ADU up to 800 sq ft, get "streamlined" review and need only a building permit. No parking is required. The rules are in Municipal Code Chapter 19.79, last amended by an ordinance adopted July 28, 2026. Planning questions go to (408) 730-7440. [1][2][3]

Sunnyvale at a glance
ADUs allowedYes, on residential and residential mixed-use lots with a single-family or multifamily home [1][3]
Units on a single-family lotUp to 3: 1 new construction ADU + 1 conversion ADU + 1 JADU (not both an in-house conversion and an attached ADU) [1][2]
Max size, new ADU1,000 sq ft (single-family lots), no limit on bedrooms; conversions have no maximum [1]
Minimum size150 sq ft [1]
HeightDetached: 16 ft; 18 ft near major transit (+2 ft for matching roof pitch) or on multistory multifamily lots. Attached: 25 ft or the main building's limit [1]
Side and rear setbacks4 ft for new construction [1]
ParkingNone required; removed covered parking need not be replaced [1]
ReviewBuilding permit only for ADUs up to 800 sq ft, conversions and JADUs; a ministerial MPP first for new ADUs over 800 sq ft on single-family lots [1][2]
Impact feesTransportation impact fee only over 750 sq ft; school fee for new ADUs of 500 sq ft or more [1][3]
Pre-approved plansYes; ADU Plans Gallery, processed within 30 days [2][4]
Short-term rentalNot allowed for ADUs approved on or after January 1, 2020 [1]
Selling an ADU separatelyNo, except under Gov. Code 66341; the city has not opted into ADU condos [1]
On this page
  1. At a glance
  2. What you can build in Sunnyvale
  3. Streamlined vs. non-streamlined review
  4. Size, height and setbacks
  5. Parking
  6. Fees and utilities
  7. How long it takes
  8. Fire and building requirements
  9. Garage conversions, junior ADUs and legalization
  10. Renting, selling and lot splits
  11. Permit steps
  12. Pre-approved plans
  13. Who to call
  14. Questions people ask

What you can build in Sunnyvale

ADUs are allowed on residential and residential mixed-use lots with an existing or proposed single-family home or multifamily building. Sunnyvale counts a duplex as multifamily. Several detached homes on one lot count as single-family. Townhomes on their own lots may count as single-family too.

ADUs are also allowed on properties in the city's Heritage Resource Inventory, with no extra permit or public review. Your approval can't be conditioned on fixing nonconforming zoning conditions or unpermitted structures that aren't a health and safety threat and aren't affected by the ADU. [1][2][4]

Streamlined vs. non-streamlined review

Sunnyvale sorts ADUs into two review tracks:

Non-streamlined ADUs must also meet extra rules: the zone's front setbacks, 5 feet from the main home and other accessory buildings (detached), an entrance not on the same street-facing wall as the house, matching materials for attached ADUs, and, for second-floor units, solar access rules, plus window privacy for second-story windows near side and rear lot lines (sills at least 5 feet up or obscured glass). Area over 800 sq ft counts toward lot coverage and floor area ratio. [1][2][3]

Size, height and setbacks

A new construction ADU on a single-family lot can be up to 1,000 sq ft, with no limit on bedrooms. Every ADU must be at least 150 sq ft. Sunnyvale measures ADU area "from the outside dimensions of a building or wall." Up to 800 sq ft of each ADU is exempt from lot coverage and floor area limits. Conversion ADUs have no maximum size, and a converted accessory building can grow by up to 150 sq ft for a way in and out. A JADU can be up to 500 sq ft.

Height is measured from the average finished grade within 5 feet of the building:

Setbacks. New construction needs 4 feet from side and rear lot lines. Less is allowed if you rebuild in the same spot and size as an existing structure you demolish. ADUs can't go in easements that bar permanent structures. [1][3]

Parking

Sunnyvale requires no off-street parking for an ADU. You don't have to replace covered parking you remove or demolish to build an ADU or to convert space into one. [1]

Fees and utilities

Your building permit fee depends on your ADU's size. Non-streamlined ADUs also pay the Planning Division's MPP fee. The city's ADU Calculator gives a rough estimate of costs, fees and rents.

Sunnyvale's code says no impact fees apply to an ADU "less than 750 square feet." State law sets the line at 750 sq ft or less of interior living space, with fees proportional to the main home above that. For utility billing, a single-family home with an ADU is billed at two-unit multifamily rates once the ADU is finished. See our ADU cost guide and financing guide. [1][3][4][5]

How long it takes

Sunnyvale's code repeats state law: the city must tell you within 15 business days whether your application is complete, and approve or deny a complete application within 60 days when there's already a home on the lot. The city's toolkit estimates 1 to 6 months for permitting and 2 to 12 months for construction. Pre-approved plans from the city's gallery are processed within 30 days. See our ADU permit process guide. [1][4]

Fire and building requirements

The city's brochure lists these building rules for ADUs on single-family lots:

For multifamily ADUs, contact the Building Division at (408) 730-7444. [3]

Garage conversions, junior ADUs and legalization

You can convert part of your home, an attached garage, or an existing accessory building into a conversion ADU with no maximum size. Conversions get streamlined review. See our garage conversion guide.

A junior ADU must be inside the walls of a single-family home, which can include an attached garage. It can't be built as a new addition or in a detached building. It needs an efficiency kitchen. If it shares a bathroom with the house, it needs an inside connecting door, and the owner must live in the JADU or the house. Before the permit is issued, you record a covenant that the JADU won't be sold separately, stays within 500 sq ft, and is rented only for terms longer than 30 days. The code requires owner occupancy when the JADU shares a bathroom, which matches state law since 2026. But the required covenant also says one unit on the lot "shall remain owner-occupied," so if your JADU has its own bathroom, ask the Planning Division how this applies.

If you built an ADU or JADU inside a permitted structure before January 1, 2020, you can apply to legalize it. The city "may use reduced development standards" if the unit is safe to live in. You can also ask for a five-year deferral of enforcement through the Community Development Department. [1][2][3][5]

Renting, selling and lot splits

You can rent an ADU separately from the main home. ADUs approved on or after January 1, 2020, can't be used as short-term rentals. An ADU can't be sold separately except under Gov. Code 66341, and the city "has not elected to allow" ADU condominiums under Gov. Code 66342.

If you split your lot under SB 9 (Sunnyvale's urban lot split rules), each new lot can have one single-family home plus one ADU or JADU, for two units at most. If a lot already has two "dual urban opportunity units," no ADUs are allowed. See our SB 9 lot split guide.

In December 2022, HCD, the state housing agency, found Sunnyvale's 2021 ADU ordinance out of compliance on points including a rule barring the ADU entrance from facing the street on the same wall as the house. The city adopted a new ADU chapter in April 2025 (Ordinance 3240-25) and amended it in July 2026 (Ordinance 3258-26); the entrance rule now applies only to non-streamlined ADUs. See our California ADU law overview. [1][6]

Permit steps in Sunnyvale

  1. Check your lot type and ADU options

    Read the Sunnyvale ADU Brochure and the ADU Toolkit to see whether your lot counts as single-family or multifamily and which ADUs you can add. [2][3]

  2. Talk to the Permit Center

    Call the Planning Division at (408) 730-7440 or the Permit Center at (408) 730-7444, or visit the One-Stop Permit Center at City Hall, 456 W. Olive Ave. Staff explain the process and documents you need. [3][7]

  3. Design the ADU or pick a pre-approved plan

    Work with an architect or contractor, or choose a design from the ADU Plans Gallery and contact its designer. [2][4]

  4. Apply for an MPP first if over 800 sq ft

    For a new ADU over 800 sq ft on a single-family lot, apply online for a Miscellaneous Plan Permit. A planner contacts you and sends an invoice; review typically takes 2 to 4 weeks after you pay. [2][3]

  5. Apply for the building permit online

    Submit plans and pay fees through the city's E-OneStop online permitting system, which you also use to answer comments and schedule inspections. See the Permit Center page for help. [4][7]

  6. Respond to plan review and get your permit

    Answer plan review comments and resubmit as needed. The city issues the permit once all reviewers approve and fees are paid. For a JADU, record the deed restriction covenant before issuance. [1][4]

  7. Build and pass inspections

    Post your approved construction documents on site and schedule inspections as you build. The city finals the permit when the work matches the plans. [4]

Pre-approved and sample plans

Who to call

Questions people ask

How big can an ADU be in Sunnyvale?

A new construction ADU on a single-family lot can be up to 1,000 sq ft. ADUs up to 800 sq ft get streamlined review; larger ones need a ministerial Miscellaneous Plan Permit first. Conversion ADUs have no maximum size, and JADUs can be up to 500 sq ft. [1]

How many ADUs can I build in Sunnyvale?

Up to three on a lot with one single-family home: one new construction ADU, one conversion ADU and one JADU. You can't have both a conversion inside the house and an attached new ADU. [1][2]

Does Sunnyvale require parking for an ADU?

No. No off-street parking is required, and you don't have to replace covered parking you remove to build the ADU. [1]

What fees does Sunnyvale charge for an ADU?

Building permit fees based on size, plus a transportation impact fee for ADUs over 750 sq ft and a school impact fee for new ADUs of 500 sq ft or more. Incremental sewer and water connection fees are waived for single-family ADUs. [3][4]

How tall can a detached ADU be in Sunnyvale?

16 feet on most single-family lots, or 18 feet within a half mile walk of a major transit stop or high-quality transit corridor (plus 2 feet for a roof matching the main home). ADUs are limited to two stories. [1]

Can I use my Sunnyvale ADU as an Airbnb?

No. ADUs approved on or after January 1, 2020, can't be used as short-term rentals. [1]

Sources (7)
  1. Sunnyvale Municipal Code Chapter 19.79 Accessory Dwelling Units (Ord. 3240-25; Ord. 3258-26, 7/28/2026), City of Sunnyvale (eCode360). Accessed October 9, 2026.
  2. Accessory Dwelling Units, City of Sunnyvale, Permit Center. Accessed October 9, 2026.
  3. Sunnyvale Homeowners: Interested in Building an Accessory Dwelling Unit? (ADU Brochure), City of Sunnyvale, Community Development Department. Accessed October 9, 2026.
  4. Sunnyvale ADU Toolkit, City of Sunnyvale, Community Development Department. Accessed October 9, 2026.
  5. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 9, 2026.
  6. Review of Sunnyvale's Accessory Dwelling Unit (ADU) Ordinance under State ADU Law (December 9, 2022), California Department of Housing and Community Development. Accessed October 9, 2026.
  7. Permit Center, City of Sunnyvale, Planning and Building. Accessed October 9, 2026.