Building an ADU in Menlo Park, California

City code and California law · Last reviewed October 10, 2026

Menlo Park allows ADUs in every zoning district that allows homes, and junior ADUs in single-family zones. A new ADU ordinance (Ordinance 1129) took effect July 10, 2026. On a single-family lot you can build one conversion ADU, one junior ADU and one new detached ADU of up to 800 square feet, and the city requires no parking for ADUs. You apply through a building permit, and on a lot with an existing home the city must decide a complete application within 60 days. [1][2][3]

Menlo Park at a glance

ADUs on a single-family lot
Up to three state-mandated units: one conversion ADU, one junior ADU and one detached ADU up to 800 sq ft [1]
Locally regulated ADUs
One per lot: up to 850 sq ft (one bedroom or less) or 1,000 sq ft More than one bedroom [1]
Attached ADU limit
Also capped at 50% of the existing home's interior livable space [1]
Junior ADU size
150 to 500 sq ft of interior livable space, inside the house [1]
Height
Detached 16 ft (18 ft near a major transit stop, plus 2 ft for a matching roof pitch) Attached 25 ft or the zone limit if lower [1]
Side and rear setbacks
4 ft None for conversions of existing space [1]
Parking
None required Lost garage or carport spaces need not be replaced [1]
Impact fees
None for an ADU of 750 sq ft or less State law [6]
Review deadlines
Completeness answer in 15 business days, then approve or deny within 60 calendar days [1][3]
Short-term rental
Not allowed Rentals must be at least 30 days [1]
Owner occupancy
Not for ADUs For a junior ADU only if it shares a bathroom with the house [1][6]
On this page
  1. At a glance
  2. What you can build in Menlo Park
  3. Size, height and setbacks
  4. Parking
  5. Fees
  6. How long it takes
  7. Junior ADUs and garage conversions
  8. Renting it out
  9. Legalizing an unpermitted ADU
  10. SB 9 lots
  11. Permit steps
  12. Pre-approved plans
  13. Who to call
  14. Questions people ask

What you can build in Menlo Park

Menlo Park's ADU rules are in Chapter 16.79 of the zoning code. The City Council adopted a new version, Ordinance 1129, on June 9, 2026, and the city says it took effect July 10, 2026. The city also says California's housing department (HCD) told it on June 15, 2026 that the ordinance "is in substantial compliance with State ADU law." You can read it on the city's ADU Ordinance update page.

ADUs are a permitted use in all zoning districts that allow single-family, multifamily or mixed-use homes. Junior ADUs (JADUs) are allowed in all single-family zones. The ordinance sorts ADUs into two groups:

On a lot with an apartment building, you can convert non-living space such as storage rooms, attics, basements or garages into at least one ADU, up to 25% of the existing units. You can also add up to eight detached ADUs on a lot with an existing multifamily building, but no more than the number of existing units, or two detached ADUs with a proposed multifamily building.

ADUs are approved ministerially, meaning staff review without a public hearing. Projects that need a use permit to modify the standards must finish that discretionary review first. For the statewide rules, see our California ADU guide. [1][2][3]

Size, height and setbacks

State-mandated detached ADU: up to 800 sq ft of interior livable space, at least 4 ft from the side and rear lot lines. Height is 16 ft, or 18 ft within a half-mile walk of a major transit stop or high-quality transit corridor, plus 2 more feet if the roof pitch matches the main house.

Locally regulated ADUs (Table 16.79.070(1)):

Guaranteed allowance: floor area limits, floor area ratio, building coverage, open space and parking rules can't block one locally regulated ADU of at least 800 sq ft with 4-ft side and rear setbacks. If you use this allowance, the main house's building permit must get its final inspection before the ADU's.

Conversions: no setback is required for existing living area or an existing accessory building converted to an ADU, or for a structure rebuilt in the same place and size. Additions beyond the footprint (up to 150 sq ft for getting in and out) must meet the 4-ft side and rear setbacks. [1]

Parking

Menlo Park requires no parking for ADUs or JADUs. When a garage, carport or covered parking structure is torn down or converted to build an ADU, "those off-street parking spaces need not be replaced." If you want to keep parking, you can provide it as tandem parking on a driveway. [1]

Fees

ADU applications must be "accompanied by the appropriate fee," and an ADU is permitted through a building permit. Building and planning fees come from the city's Master Fee Schedule, which the City Council approved on April 28, 2026. It sets building plan check and permit fees by occupancy type and size, and passes credit and debit card processing fees through to the payer.

Impact fees: Under state law, no city, special district or water company may charge impact fees on an ADU with 750 sq ft or less of interior livable space, or a JADU of 500 sq ft or less. Above those sizes, impact fees must be in proportion to the unit's size compared with the main house. Menlo Park's fee schedule lists a "Building Construction Street Impact Fee" of 0.58% of project valuation on construction projects over $10,000 (residential alterations and repairs excluded). The schedule doesn't say how this applies to small ADUs, so ask the Building Division before you budget for it.

School fees: State law lets school districts charge fees on ADUs larger than 500 sq ft of interior livable space.

Utilities: An ADU or JADU created inside existing or proposed space under state law (Gov. Code 66323(a)(1)) can't be required to install a new or separate utility connection or pay a related connection fee or capacity charge, unless it is built with a new single-family home or approved for separate sale. An ADU built with a new home needs its own connection, and it may be charged a connection fee or capacity charge in proportion to its size or plumbing fixtures. For other ADUs, ask the Building Division and your water and sewer providers what applies. You must also submit a letter from the sanitary district confirming there is enough sewer capacity for the ADU.

For budgeting help, see our ADU cost guide and ADU financing guide. [1][4][5][6]

How long it takes

Since January 1, 2026, Menlo Park reviews ADU applications in two steps:

You can appeal a completeness decision or a denial in writing to the Planning Commission within 15 calendar days. The commission must decide within 60 business days. See our ADU permit process guide for the general steps. [1][3][7]

Junior ADUs and garage conversions

A JADU must be between 150 and 500 sq ft of interior livable space and sit entirely inside a single-family home. It may add up to 150 sq ft beyond the house's walls, only for getting in and out. It needs a separate entrance and a permanent efficiency kitchen. A JADU without its own bathroom must have both a separate entrance and an interior door into the main living area. No parking is required.

Owner occupancy: only when the JADU shares a bathroom with the house. In that case the owner must live in the house or the JADU. The owner must record a deed restriction that bars selling the JADU separately from the house. A JADU may be rented, but not for less than 30 consecutive days.

Garage conversions: a garage or other accessory building can become an internal ADU, with up to 150 sq ft added for getting in and out. If the existing building wouldn't otherwise meet the location or height rules for an ADU, the city's checklist asks you to show it was legally permitted, for example with a city building permit or a San Mateo County property assessment record. See our junior ADU guide and garage conversion guide. [1][7]

Renting it out

You may rent an ADU separately from the main house, but "not for a period of less than thirty consecutive days." State-mandated ADUs and JADUs carry the same 30-day minimum, so short-term rentals are out. An ADU can't be sold separately from the main house unless the conditions in state law (Gov. Code 66341) are met; HCD calls this "a narrow exception" for homes built by a qualified nonprofit corporation. [1][6]

Legalizing an unpermitted ADU

If your ADU or JADU was built without permits before January 31, 2023, the city may not deny a permit to legalize it because of building standard violations or because it doesn't meet the ADU chapter, unless the Community Development Director finds a fix is needed to protect health and safety. You won't be required to pay impact fees or connection or capacity charges, except in limited cases where utility work is needed for safety. Before applying, you may get a confidential code inspection from a licensed contractor. Proof of the build date can include utility records, assessor records, aerial images, dated photos, contractor invoices, rental agreements or insurance records. [1]

SB 9 lots

SB 9 lets you build two homes on a single-family lot and split it once. In Menlo Park it applies in the R-E-S, R-E, R-1-S, R-1-S (FG), R-1-U and R-1-U (LM) zones. On a lot that is not split, the city says ADU law can be combined with SB 9 for up to four units: two main homes and two ADUs. The ADU ordinance doesn't allow ADUs or JADUs on a lot that has both an approved urban lot split and an approved two-unit development. Each lot from an urban lot split must be at least 1,200 sq ft, and the applicant must sign an affidavit to live in one unit for at least three years. The city is updating its SB 9 rules; see the SB 9 Projects page and our SB 9 guide. [1][8]

Permit steps in Menlo Park

  1. Talk to the city first

    Staff recommend coming to the public information counter to discuss ADU rules with Planning, Building and Engineering before you apply. Planning is at 650-330-6702, and you can make an appointment online. [3][9][10]

  2. Design to Chapter 16.79

    Have plans drawn that show compliance with the ADU chapter and your zone: site plan, floor and roof plans, elevations, sections, floor area and building coverage diagrams, and a boundary and topographic survey. [7]

  3. Gather engineering and tree documents

    ADUs over 500 sq ft need grading, drainage and improvement plans. Add an impervious area worksheet, plus flood zone or creek documents and an arborist report if they apply. [7]

  4. Submit the building permit application

    Submit the building permit application with the city's ADU Completeness Checklist, initialing each item, and pay the application fee. [1][3][7]

  5. Record a JADU deed restriction

    For a junior ADU, record the deed restriction barring separate sale and limiting the JADU's size and features. [1][7]

  6. Completeness review and decision

    The city answers on completeness within 15 business days, then approves or denies within 60 calendar days. Track your permit on the city's Accela portal. [1][3][11]

  7. Build and pass inspections

    Schedule inspections online or by calling 650-330-6767. [11]

Pre-approved and sample plans

Who to call

Questions people ask

How big can an ADU be in Menlo Park?

A state-mandated detached ADU can be up to 800 sq ft. One larger, locally regulated ADU is allowed per lot: up to 850 sq ft with one bedroom or less, or 1,000 sq ft with more than one bedroom. Attached ADUs are also capped at 50% of the house, and accessible ADUs get an extra 100 sq ft. [1]

How many ADUs can I build in Menlo Park?

On a single-family lot, up to three state-mandated units: one conversion ADU, one junior ADU and one detached ADU of up to 800 sq ft. Only one locally regulated ADU, such as an attached addition, is allowed per lot. [1]

Does Menlo Park require parking for an ADU?

No. The 2026 ordinance requires no parking for ADUs or JADUs, and garage or carport spaces lost to an ADU don't have to be replaced. [1]

How long does a Menlo Park ADU permit take?

The city answers on completeness within 15 business days, then must approve or deny a complete application within 60 calendar days on a lot with an existing home. If it misses the 60 days, the application is deemed approved. [1][3]

Can I rent my Menlo Park ADU on Airbnb?

No. ADUs and JADUs may not be rented for less than 30 consecutive days. [1]

Sources (13)
  1. Ordinance No. 1129: Chapter 16.79 (Accessory Dwelling Units), adopted June 9, 2026, City of Menlo Park. Accessed October 10, 2026.
  2. ADU Ordinance update, City of Menlo Park Planning Division. Accessed October 10, 2026.
  3. What is the permit process?, City of Menlo Park Planning Division. Accessed October 10, 2026.
  4. Master Fee Schedule, City of Menlo Park Administrative Services. Accessed October 10, 2026.
  5. 2026 Approved Master Fee Schedule, City of Menlo Park. Accessed October 10, 2026.
  6. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
  7. Accessory Dwelling Unit (ADU) Application Checklist (3-19-2026), City of Menlo Park Planning Division. Accessed October 10, 2026.
  8. SB 9 Projects, City of Menlo Park Planning Division. Accessed October 10, 2026.
  9. Planning, City of Menlo Park Community Development. Accessed October 10, 2026.
  10. Accessory dwelling units, City of Menlo Park Planning Division. Accessed October 10, 2026.
  11. Building, City of Menlo Park Community Development. Accessed October 10, 2026.
  12. Preapproved ADUs, City of Menlo Park Planning Division. Accessed October 10, 2026.
  13. Preapproved ADUs: Information for homeowners, City of Menlo Park Planning Division. Accessed October 10, 2026.