Building an ADU in Newport Beach

City code and California law · Last reviewed October 10, 2026

Newport Beach allows ADUs and junior ADUs in all residential and mixed-use zones, with no minimum lot size. Outside the Coastal Zone, a new attached or detached ADU can be up to 850 sq ft (studio or one bedroom) or 1,000 sq ft (two or more bedrooms), with 4-foot side and rear setbacks. The city must act on a complete application within 60 days. Lots in the Coastal Zone follow a separate set of rules: a Coastal Development Permit may be needed, and garage parking removed for an ADU must be replaced. [1][2][3]

Newport Beach at a glance

Which rules apply
Municipal Code 20.48.200 (amended 2025, effective Sept. 9, 2025) In the Coastal Zone, 21.48.200 [1][2][4]
Number on a single-family lot
One ADU and one junior ADU under city rules State law also allows a converted ADU, a new detached ADU of up to 800 sq ft and a JADU together [1][3][7]
Attached or detached ADU size
Up to 850 sq ft (studio or 1 bedroom) or 1,000 sq ft (2+ bedrooms) Conversions of existing space have no size cap [1][6]
Junior ADU
Up to 500 sq ft, within or attached to a single-family home One per lot [1]
Height (detached)
16 ft 18 ft near major transit (plus 2 ft to match the roof pitch) or on a lot with a multi-story apartment building [1]
Side and rear setbacks
4 ft (or less if the zone allows less) None for conversions of existing space [1][6]
Parking
At most 1 space per ADU None for JADUs, conversions, or near transit and in other listed cases [1]
Coastal Zone
A Coastal Development Permit may be required, and converted or demolished garage parking must be replaced [2][6]
City permit fees
Plan check about $850-$1,700 and building permit about $850-$2,100, per the city's ADU site [8]
Owner occupancy
None for ADUs For a JADU the city requires the owner to live on site (state law since 2026: only if the JADU shares a bathroom) [1][7]
Approval deadline
Approve or deny within 60 days of a complete application [1][7]
Short-term rental
Not allowed: no rentals of 30 days or less [1]
On this page
  1. At a glance
  2. Which rules apply in Newport Beach
  3. What you can build
  4. Size, height and setbacks
  5. Parking and garage conversions
  6. Building in the Coastal Zone
  7. Fees
  8. How long it takes
  9. Junior ADUs, owner occupancy and deed restrictions
  10. Renting, selling and legalizing an existing unit
  11. Permit steps
  12. Pre-approved plans
  13. Who to call
  14. Questions people ask

Which rules apply in Newport Beach

Newport Beach has two ADU ordinances. Section 20.48.200 of the Municipal Code applies citywide outside the Coastal Zone. Section 21.48.200, part of the city's Local Coastal Program rules, applies inside the Coastal Zone. The city's ADU rules page says the current citywide rules were "Adopted August 26, 2025 and effective September 9, 2025."

Before that update, the state housing agency (HCD) reviewed the city's 2023 ordinance. Its October 2024 letter listed 13 ways it failed to comply with state law. Examples included owner-occupancy rules and deed restrictions on ADUs, a ban on selling ADUs separately in any case, and a rule that "Only one (1) of the categories" of ADU could be used per lot. The 2025 citywide rules no longer require owner occupancy for ADUs, and they say the unit limits apply "Unless precluded by Government Code Section 66323." The Coastal Zone section still contains the "Only one of the categories" wording.

The city's ADU website asks you to "Confirm all details with City staff while planning your ADU." Call the Planning Division at 949-644-3204. [1][2][4][5]

What you can build

ADUs and JADUs are allowed in every residential and mixed-use zone, and there's no minimum lot size. The city's ADU site says "Homeowners can build both an ADU and a JADU on their property."

[1][3][6][7]

Size, height and setbacks

These are the citywide rules in section 20.48.200. The Coastal Zone section uses the same size, height and setback numbers, but a larger setback can be required to protect coastal resources.

[1][2][5][6]

Parking and garage conversions

Outside the Coastal Zone, the city can require at most one parking space for each ADU. It can be tandem or on an existing driveway, but not in the front setback unless the driveway there is at least 20 feet deep. JADUs need no parking.

No parking is required for an ADU that is inside the house or converted from an existing accessory structure, or that is:

State law requires that last exemption only when the ADU or the lot also meets one of the other exemptions; the city's list doesn't include that condition. Confirm with the Planning Division how it applies to your lot.

Garage conversions. Outside the Coastal Zone, the code says garage, carport and parking spaces removed or converted for an ADU "are not required to be replaced," and the same applies when a garage becomes a JADU. The city's ADU site and 2026 summary chart say replacement parking is required for a JADU garage conversion citywide. HCD's 2024 letter said requiring replacement parking when covered parking is converted into a JADU "is inconsistent with the Law." Ask Planning which rule it applies. Inside the Coastal Zone, garage parking removed for an ADU must be replaced. See our garage conversion guide. [1][2][3][5][6][7]

Building in the Coastal Zone

If your lot is in the Coastal Zone, section 21.48.200 applies instead of the citywide section. Use the city's Address Search Tool to check.

HCD's handbook says state ADU law applies in the Coastal Zone but doesn't "alter or lessen" Coastal Act protections. It also says that when a certified local coastal program has ADU rules, the city must approve or deny a coastal permit for an ADU within 60 days of a complete application when there's already a home on the lot, and isn't required to hold a public hearing. [2][5][7][8]

Fees

The city's ADU site lists these typical city fees:

Under state law, an ADU with 750 sq ft of interior livable space or less pays no impact fees, and a larger one pays in proportion to the size of the house. ADUs under 500 sq ft don't pay school impact fees. The city points to the Orange County ADU calculator for an estimate. For typical building costs see our ADU cost guide. [1][7][8]

How long it takes

The code says a building permit for an ADU or JADU "shall be considered and approved ministerially, without discretionary review or a hearing, within sixty (60) days" after the city finds the application complete. That clock pauses if you ask for a delay. If you apply together with a new house, the city can wait until it decides on the house.

In practice, the city's ADU site says review comments come back "within 10-20 days," and "Most projects require 2-3 rounds of review." It puts permitting at 1 to 6 months and a whole ADU project at 12 to 18 months. State law also requires a written completeness decision within 15 business days. See our ADU permit process guide. [1][7][8]

Junior ADUs, owner occupancy and deed restrictions

A JADU is up to 500 sq ft, within or attached to a single-family home, with its own exterior entrance. It may also connect to the house inside. It can share a bathroom with the house and needs at least an efficiency kitchen. See our junior ADU guide.

Owner occupancy. The city doesn't require you to live on the property to have an ADU. For a JADU, the code says an owner must live in either the house or the JADU. Since 2026, state law requires that only if the JADU shares bathroom facilities with the house. Ask Planning how it applies to a JADU with its own bathroom.

Deed restrictions. Outside the Coastal Zone, the code requires a recorded deed restriction for a JADU only. The city's permit page still lists a signed, notarized deed restriction (no separate sale and no short-term rental) for ADUs. HCD's handbook says a city "cannot impose a deed restriction on an ADU." In the Coastal Zone, the coastal section requires one for both ADUs and JADUs. Confirm with your planner which form you'll be asked to record. [1][2][3][6][7][8]

Renting, selling and legalizing an existing unit

ADUs and JADUs may be rented, but not for 30 days or less, so short-term rentals such as Airbnb aren't allowed. An ADU can't be sold separately from the house, except under a state law for homes built by qualified nonprofits.

Unpermitted units. The city's Safe ADU program helps legalize ADUs and JADUs built without permits. The city says "Any ADU built before 2020 qualifies," and that the unit must be brought up to the current building code but not current zoning standards. In the Coastal Zone the unit can't harm coastal resources such as public views, access or habitat. You can ask questions without giving your address at the Permit Center or through the ADU Assist Form. [1][7][9]

Permit steps in Newport Beach

  1. Check your lot

    Look up your zoning, utility providers and whether you're in the Coastal Zone on the city's Address Search Tool. [3][8]

  2. Talk to Planning

    Walk in to the Permit Center at 100 Civic Center Drive (1st floor, Bay C), call 949-644-3204, or use the ADU Assist Form. The city says a meeting before you apply isn't required but may save time. [8][10]

  3. Get a design or pick a standard plan

    Hire a designer, or use one of the city's ADU Standard Plans. With a standard plan, ask a Building Engineer at 949-644-3265 which supplemental documents you need. [11]

  4. Apply for a Coastal Development Permit if needed

    In the Coastal Zone, you may first need a Coastal Development Permit unless your project is exempt or excluded. [2][8]

  5. Prepare the application package

    Combine the plan check and building permit applications with a grant deed and the city's Housing Questionnaire. The city's permit page also lists a signed, notarized deed restriction; HCD says a city can't impose a deed restriction on an ADU, so confirm with your planner which form applies. [7][8]

  6. Submit and pay plan check fees

    Submit in person at the Permit Center; the city's standard plans page says you can also apply through the CiViC portal. Plan check fees are due at submission. [8][11]

  7. Answer review comments

    The city returns comments within 10 to 20 days per round; most projects need 2 to 3 rounds. This is also a good time to request an address for the ADU. [8]

  8. Get the permit, build and pass inspections

    Pay building permit and other fees when the permit is issued. If the ADU is near overhead power lines or an easement, you need a Southern California Edison sign-off before the final permit. [3][8]

Pre-approved and sample plans

Who to call

Questions people ask

Does Newport Beach allow ADUs?

Yes. ADUs and junior ADUs are allowed in all residential and mixed-use zones, with no minimum lot size, and are approved through a building permit without a hearing. In the Coastal Zone you may also need a Coastal Development Permit. [1][2][3]

How big can an ADU be in Newport Beach?

A new attached or detached ADU can be up to 850 sq ft for a studio or one bedroom and 1,000 sq ft for two or more bedrooms. A JADU can be up to 500 sq ft. An ADU converted from existing space has no size cap. [1][6]

Do I need a Coastal Development Permit for an ADU?

If your lot is in the Coastal Zone, usually yes, unless the project is exempt or excluded. Check your address on the city's Address Search Tool, then ask the Planning Division at 949-644-3204. [2][3][10]

Can I Airbnb my ADU in Newport Beach?

No. ADUs and JADUs can't be rented for 30 days or less. [1][3]

Does Newport Beach have pre-approved ADU plans?

Yes. The city offers five ADU Standard Plans: three detached floor plans (448, 504 and 672 sq ft) in three styles, plus plans to convert a one-car or two-car garage. You still need a site plan and some other site-specific documents. [11]

Can I legalize an unpermitted ADU in Newport Beach?

Usually, through the Safe ADU program. The city says any ADU built before 2020 qualifies if it's brought up to the current building code; it doesn't have to meet current zoning standards. [9]

Sources (11)
  1. Newport Beach Municipal Code § 20.48.200 Accessory Dwelling Units (through Ord. 2025-20), City of Newport Beach (eCode360). Accessed October 10, 2026.
  2. Newport Beach Municipal Code § 21.48.200 Accessory Dwelling Units (Local Coastal Program Implementation Plan), City of Newport Beach (eCode360). Accessed October 10, 2026.
  3. Learn the Rules, City of Newport Beach. Accessed October 10, 2026.
  4. Newport Beach ADU Rules, City of Newport Beach. Accessed October 10, 2026.
  5. Review of Newport Beach's Accessory Dwelling Unit (ADU) Ordinance under State ADU Law (October 1, 2024), California Department of Housing and Community Development. Accessed October 10, 2026.
  6. Accessory Dwelling Unit Ordinance Summary (2026), City of Newport Beach. Accessed October 10, 2026.
  7. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
  8. Permit, City of Newport Beach. Accessed October 10, 2026.
  9. Safe ADU Newport Beach, City of Newport Beach. Accessed October 10, 2026.
  10. Contact Us, City of Newport Beach. Accessed October 10, 2026.
  11. ADU Standard Plans, City of Newport Beach. Accessed October 10, 2026.