Getting it permitted

How long it takes to build an ADU

Checked against state laws and official agency sources · Last reviewed October 10, 2026

It depends on your city, your design and your builder. City guides that give estimates vary widely: Newport Beach, California, says most ADU projects take 12 to 18 months, and Boston expects 6 to 12 months for construction alone. A few states set deadlines for the permit part. In California, the city must approve or deny a complete application within 60 days when there is already a home on the lot, or it is deemed approved. Pre-approved plans can shorten review. [1][2][3]

On this page
  1. The stages, and what cities say each one takes
  2. Permit review and corrections
  3. State deadlines for permit review
  4. California: 15 business days, then 60 days
  5. If a California city misses the deadline
  6. Connecticut, Minnesota, North Carolina and Washington
  7. Pre-approved and permit-ready plans
  8. Construction, inspections and move-in
  9. Questions people ask

The stages, and what cities say each one takes

Most ADUs go through the same stages. Each city sets its own process, and only some publish time estimates. These are the estimates from city ADU guides we checked:

These are rough planning figures from each city, not promises, and they cover only these cities. Ask your own building department what to expect. Our ADU permit process guide walks through each step. [1][2][4][5]

Permit review and corrections

Review usually happens in rounds. The city checks your plans, sends comments, and you revise and resubmit. Newport Beach says it returns comments within 10 to 20 days and that "Most projects require 2-3 rounds of review." Escondido says ADU applications are reviewed in cycles, with each cycle in its pre-approved ADU program "lasting up to 30 days," and "Plan review can take multiple cycles." Boston says review takes longer if you need to update plans, send more documents, or get zoning relief.

That's why a complete, code-compliant first submittal saves the most time. How fast you and your designer answer comments counts too. [1][2][5]

State deadlines for permit review

Some state laws set how long a city has to act. These are the deadlines in the laws on our state pages. If your state isn't listed, ask your city or county how long review takes.

Details and conditions for each state are below. [3][6][7][8][9][10][11]

California: 15 business days, then 60 days

California's ADU law (Government Code 66317) sets two clocks:

Conditions to know:

[3]

If a California city misses the deadline

The statute answers this directly: "If the local agency has not approved or denied the completed application within 60 days, the application shall be deemed approved." For the completeness check, a missed 15-business-day deadline means the application is deemed complete.

The 60-day rule depends on its conditions: a completed application and an existing home on the lot. Any delay you asked for pauses the clock. Ask your city how it counts the days on your application, and use the appeal process if you disagree. The California page explains how to contact HCD, the state housing agency that enforces ADU law. [3]

Connecticut, Minnesota, North Carolina and Washington

Connecticut. State law (General Statutes 8-2o) says a town's as-of-right review of an accessory apartment "shall require that a decision on any such application be rendered not later than sixty-five days after receipt of such application by the applicable zoning commission." You may consent to "one or more extensions of not more than an additional sixty-five days," or withdraw the application. Towns could opt out of the accessory apartment rules, this deadline included, only before January 1, 2023, so ask your town whether it opted out.

Minnesota. Minnesota Statutes 15.99 says an agency "must approve or deny within 60 days a written request relating to zoning" for a permit or other approval, and "Failure of an agency to deny a request within 60 days is approval of the request." The clock starts when the agency receives a request with all required information, including the fee. If something is missing, the 60 days start over only if the agency tells you in writing within 15 business days what is missing. The law covers requests relating to zoning, septic systems and a few other reviews; building permits aren't on that list. Ask your city whether your ADU application is a zoning request under this law.

North Carolina. If a city or county chooses to review residential building plans, G.S. 160D-1110 says "all initial reviews for the building permit shall be performed within 15 business days of submission of the plans." If the first review takes more than 20 business days, the local government must refund 10% of the total permit application fee for each extra business day, for up to 10 business days.

Washington. RCW 36.70B.080 sets default decision times for "project permits" in cities and counties planning under the Growth Management Act: 65 days after the application is found complete when no public notice is needed, 100 days with public notice, and 170 days with notice and a hearing, unless the local government modifies them. Days spent waiting for information you were asked to provide don't count. But a "project permit" doesn't include "permits issued based on compliance with state and local building codes," so ask your city which timeline, if any, applies to your ADU. [7][8][9][10][11]

Pre-approved and permit-ready plans

Using a plan the city has already reviewed can shorten the permit stage.

California (AB 1332). Every city and county had to set up a program to pre-approve ADU plans by January 1, 2025, and post the approved plans online. Under Government Code 65852.27, the agency must approve or deny a detached ADU application "within 30 days from the date the local agency receives a completed application" if it uses a plan pre-approved by the agency within the current building code cycle, or a plan identical to one in a detached ADU application the agency already approved in that cycle.

City examples:

Arizona. State law (ARS 9-461.20) requires cities to create pre-approved housing plans, including at least three ADU plans from July 1, 2026, and to approve or deny plans submitted to its pre-approved plan program administratively, without discretionary review. See the Arizona page.

For factory-built options, see prefab ADUs. [6][12][13][14][15]

Construction, inspections and move-in

You can't start building until the permit is issued. Bakersfield's toolkit says: "You must have your approved construction document before you can start construction." During construction you schedule inspections with the city, and the city finalizes the permit once the work is done "in accordance with the approved plans." In California, you need a certificate of occupancy before anyone lives in the ADU.

City estimates for construction range from 2 to 12 months (Bakersfield) to 6 to 14 months (Escondido). The type of ADU matters: Boston says the construction timeline "greatly depends on the type of ADU you've opted to build and the scope of work on your property." Your contractor can give you a schedule for your project. See hiring ADU help and our ADU cost guide. [2][4][5][12]

Questions people ask

How long does it take to build an ADU from start to finish?

It varies by city and project. Newport Beach, California, says most ADU projects take 12 to 18 months, and some take 24 months or more. Boston's rough guide is up to 3 months for design, up to 3 months for permitting and 6 to 12 months for construction. Ask your city for its current estimates. [1][2]

How long does a California city have to approve an ADU permit?

It must tell you within 15 business days whether your application is complete. When there is already a home on the lot, it must approve or deny a complete application within 60 days. The 60 days pause if you ask for a delay. For a detached ADU that uses a qualifying pre-approved plan, the deadline is 30 days from a completed application. [3][6]

What happens if the city misses the 60-day deadline in California?

Government Code 66317 says that if the agency hasn't approved or denied the completed application within 60 days, "the application shall be deemed approved." The rule applies to a completed application on a lot with an existing home. [3]

Do pre-approved ADU plans really save time?

They can shorten the permit stage. California requires a decision within 30 days on a complete detached ADU application that uses a qualifying pre-approved plan. Rocklin's code says 30 calendar days for pre-approved plans versus 60 for others, and Seattle says you can get a permit with one of its pre-approved plans in 2 to 6 weeks in most cases. [6][13][14]

Sources (15)
  1. Permit, City of Newport Beach (Newport Beach ADU). Accessed October 10, 2026.
  2. Frequently Asked ADU Questions, City of Boston. Accessed October 10, 2026.
  3. California Government Code section 66317, California Legislature. Accessed October 10, 2026.
  4. ADU Toolkit: Resource Guide for Accessory Dwelling Units (February 15, 2024), City of Bakersfield. Accessed October 10, 2026.
  5. PAADU Program Guidebook, City of Escondido. Accessed October 10, 2026.
  6. California Government Code section 65852.27, California Legislature. Accessed October 10, 2026.
  7. General Statutes of Connecticut, 2026 Supplement, Chapter 124, Sec. 8-2o, Connecticut General Assembly. Accessed October 10, 2026.
  8. Minnesota Statutes, section 15.99 Time Deadline for Agency Action, Minnesota Office of the Revisor of Statutes. Accessed October 10, 2026.
  9. G.S. 160D-1110, Building permits, North Carolina General Assembly. Accessed October 10, 2026.
  10. RCW 36.70B.080 Development regulations, Required timelines for review completion, Washington State Legislature. Accessed October 10, 2026.
  11. RCW 36.70B.020 Definitions, Washington State Legislature. Accessed October 10, 2026.
  12. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
  13. Rocklin Municipal Code Chapter 17.67, Accessory Dwelling Units and Junior Accessory Dwelling Units, City of Rocklin (Municode). Accessed October 10, 2026.
  14. Encouraging Backyard Cottages, City of Seattle Office of Planning and Community Development. Accessed October 10, 2026.
  15. ARS 9-461.20 Municipal housing; standard preapproved housing design plans; indemnification; definition, Arizona State Legislature. Accessed October 10, 2026.