The public cost studies we found come from California, Seattle and Portland. A 2021 UC Berkeley survey found a median ADU cost of $150,000 in California, and a 2022 City of Seattle survey found a median of $200,000 in Seattle. In Seattle's survey, attached ADUs cost less than detached ones; in a 2017 Portland survey, garage, basement and other ADU types cost less than detached ones. Besides construction, budget for design, permits, impact fees, site work and utility connections. Several states, including California, Washington, Idaho, Montana, Massachusetts and North Carolina, limit what local governments can charge in ADU fees. [1][2][3][4][5][6][7][8][9][10]
On this page
What ADUs have cost: the studies
Each study below covers one place and one period. None is a national average.
California, statewide (survey results released 2021). A research team at UC Berkeley's Center for Community Innovation ran California's first statewide survey of ADU owners. The Terner Center summarized the results on April 22, 2021:
- The median construction cost of an ADU was $150,000, or $250 per square foot.
- 37 percent of new ADUs cost less than $100,000 to build, and 71 percent cost less than $200,000.
California, by region (2020 report). An August 2020 report from the Terner Center and the Center for Community Innovation put the average California ADU cost at $167,000. It found an average of $148,000 in Los Angeles and $237,000 in the Bay Area, a gap it said was "driven largely by differences in labor costs." It also said Bay Area costs "can exceed $800 per square foot, equaling $400,000 for a 500 square foot ADU."
Seattle (2022 survey). The City of Seattle's Office of Planning and Community Development and the University of Washington surveyed owners and occupants of ADUs permitted from 2016 to 2021. Owners were asked to include design, labor, materials and permits. In the city's 2022 ADU Annual Report (March 2023):
- The median cost was $200,000 for owners with one ADU (318 responses).
- The median was $100,000 for attached ADUs (128 responses) and $230,000 for detached ADUs (189 responses).
- Answers ranged from $10,000 to $800,000 for attached ADUs and $20,000 to $650,000 for detached ones.
Portland, Oregon (2017 survey, 2019 report). Portland State University's Northwest Economic Research Center used an October and November 2017 survey of ADU owners and occupants. Its May 2019 report found a median price of $127,000 for detached ADUs, compared with a median range of $65,000 to $80,000 for garage, basement and other ADU types. It notes that garage units "can be either attached or detached."
Massachusetts (inspector reports on an undated state web page, not a study). The state's housing office (EOHLC) says early reports from building inspectors show the high cost of construction remains a major barrier. It says that labor and materials, fire separation required by the building code, and septic upgrades "can drive the total cost of an ADU to $500,000, according to some inspectors EOHLC surveyed."
We haven't found similar government or university cost studies for the other states on this site. These figures are local and several years old. Treat them as a starting point, not a quote, and get bids for your own lot. [1][2][3][11][12]
The parts of the bill
Construction is the biggest part, but not the only one. California's housing finance agency lists the "pre-development costs" of an ADU as "site prep, architectural designs, permits, soil tests, impact fees, property surveys, and energy reports." Seattle's owner survey asked about "design, labor, materials, and permits."
A simple way to budget is to price each of these separately:
- Design: plans and drawings. Some cities offer pre-approved plans for free (see below).
- Permits and plan review: set by your city or county. See our city pages and the permit process guide.
- Impact fees: one-time fees that help pay for public facilities such as parks, fire and police. Several states limit them for ADUs (see the next section).
- Utility connections: water and sewer connection fees, capacity charges or system development charges.
- Site work: site prep, soil tests and surveys.
- Construction: the building itself.
How state laws limit ADU fees
Fee rules depend on your state. These are the states on this site whose laws limit ADU fees:
- California: No impact fees on an ADU of 750 square feet of interior livable space or less, or a junior ADU of 500 square feet or less. Above 750 square feet, impact fees "shall be charged proportionately in relation to the square footage of the primary dwelling unit." HCD's example: a 1,000-square-foot ADU next to a 2,000-square-foot house "could result in 50 percent of the impact fee" for a new house. School districts may charge school fees on ADUs over 500 square feet. Starting January 1, 2027, under SB 1117 (Chapter 809, Statutes of 2026), on a lot with up to two ADUs, the proportional impact fee for an ADU over 750 square feet will be charged "only on the area in excess of 750 square feet of interior livable space." On a lot with more than two ADUs, the current proportional rule still applies.
- Washington: Inside urban growth areas, cities and counties that plan under the Growth Management Act "may not assess impact fees on the construction of accessory dwelling units that are greater than 50 percent of the impact fees that would be imposed on the principal unit."
- Idaho: By February 1, 2027, cities of more than 10,000 people must change their rules for land zoned for single-family homes (outside historic districts) to prohibit "impact fees or utility connection fees on accessory dwelling units that are greater than those imposed on other single-family dwellings."
- Montana: Cities and towns, and counties with zoning, may not "assess impact fees on the construction of an accessory dwelling unit." They may charge a one-time application fee of "up to $250 for each accessory dwelling unit," plus their usual building fees.
- Massachusetts: For a "Protected Use ADU," a city or town can't require any "impact analysis, study, report, or impact fee" that a single-family home in the same district would not need.
- North Carolina: For ADU permit applications from January 15, 2027, cities of 50,000 or more outside the coastal area may not "charge any fees in excess of those charged for the permitting of a single-family detached dwelling similar in nature."
Colorado's 2024 ADU law works differently. It still lets local governments apply a "generally applicable" impact fee to ADUs, but the state's ADU Grant Program gives grants to certified local governments, which can use them to waive or reduce ADU fees, among other uses. See our Colorado page.
For the other states, check our state page and ask your city, county and utilities what they charge. [5][6][7][8][9][10][13][18][19][20][21][22][23][24]
Utility connection fees
Water and sewer providers often charge a one-time fee to connect a new unit or to pay for system capacity. Some states limit these charges, or separate-connection rules, for ADUs:
- California: An ADU or junior ADU "shall not be considered by a local agency, special district, or water corporation to be a new residential use for purposes of calculating connection fees or capacity charges for utilities, including water and sewer service, unless the unit was constructed with a new single-family dwelling." A unit built within the space of a house or an existing accessory structure can't be required to get a new or separate connection or pay a related fee, unless it is built with a new home or sold separately. For other ADUs, the provider may require a new connection, with a fee "proportionate to the burden" of the ADU.
- Idaho: By February 1, 2027, covered cities must change their rules to bar utility connection fees for ADUs that are higher than those for other single-family homes.
- Massachusetts: A city or town "may not require a separate utility connection, such as water, sewer, electric," for a Protected Use ADU. A utility, state law, a board or commission, or a court can still require one.
- North Carolina: Covered cities may not prohibit connecting an ADU to the utilities that serve the main house, if that service "has capacity to serve both dwellings."
Elsewhere, the provider's own fee schedule applies. Ask your water and sewer provider for their exact charges early. The local examples below show what some providers charge. [5][7][9][10][13]
Local fee examples
These figures come from city fee schedules and handouts. Fees change, so confirm current amounts with the city.
- Boise, Idaho: Inside city limits, city impact fees for parks, fire and police on a dwelling unit of 700 square feet or less run from $1,384.84 (Airport and Downtown planning areas) to $2,992.72 (South planning area), plus a 1% surcharge, under the schedule effective October 1, 2025.
- Portland, Oregon: The city says system development charges (SDCs) "can add significant cost" to an ADU. It can waive them if you sign a covenant that the ADU and the house won't be used as short-term rentals for 10 years.
- Las Vegas, Nevada: The city's 2026 sewer connection charges, effective January 1, 2026, are $3,235 for each single-family dwelling unit and $1,941 for each "Guest Quarters / Casitas" structure.
- St. Paul, Minnesota: The Metropolitan Council sewer availability charge (SAC) is $2,485 per unit plus a $175 processing fee, and the parkland dedication fee is $1,200 per unit. The city's ADU handout puts the SAC and parkland fees together at up to $3,860, due when the building permit is issued.
- Fresno, California: The city's pre-approved ADU cost estimator (dated October 27, 2025) shows "Total Permit & Impact Fees" of $7,958.33 to $8,443.86 for its four smaller plans (340 to 625 square feet of living space, one of them over a garage), with impact fees marked "Less than 750 Sq. Ft. No Fees," and $15,609.99 for its 1,015-square-foot plan, which includes $5,258.66 in impact fees. These totals include a new water service and meter and a water capacity fee. School fees are extra.
[14][15][25][26][27][28][29][30]
Garage conversions and junior ADUs
The cost studies don't measure conversions directly. In Seattle's 2022 survey, attached ADUs had a median cost of $100,000, against $230,000 for detached ADUs. In Portland's 2017 survey, garage, basement and other ADU types had a median range of $65,000 to $80,000, against $127,000 for detached units; the report notes that garage units "can be either attached or detached." Neither study gives a separate figure for garage conversions alone.
In California, conversions can also cost less in fees: an ADU or junior ADU built within existing space can't be required to get a new or separate utility connection or pay a related connection fee, unless it is built with a new single-family home or sold separately. In Massachusetts, a city or town can't require a separate utility connection for any Protected Use ADU, converted or new, though a utility still can.
Junior ADUs are a California category. California law defines a junior ADU (JADU) as a unit of no more than 500 square feet of interior livable space "contained entirely within a single-family residence." A JADU of 500 square feet or less is exempt from impact fees.
For the details, see our guides to garage conversions, junior ADUs and prefab ADUs. [2][3][5][9][13]
Ways to lower design and fee costs
Pre-approved plans. Some states require cities to offer ready-made ADU plans that are already reviewed, and some cities offer them:
- California: Each local agency had to "develop a program for the preapproval of ADU plans by January 1, 2025." For a detached ADU using a pre-approved plan, it must approve or deny the application within 30 days.
- Arizona: Under ARS 9-461.20, beginning July 1, 2026, cities and towns must create at least three pre-approved ADU plans, of 200, 600 or 1,000 square feet, in single-family areas that allow ADUs. They must approve or deny these plans administratively, "without discretionary review." Phoenix offers an ADU Standard Plan Library that is "free to use for City of Phoenix residents," though designs marked "IN REVIEW" are not yet available.
- Seattle: The city's 2023 ADU report says permits using its pre-approved detached ADU (backyard cottage) plans averaged 80 days from intake to issuance in 2020-2023, against 133 days for other detached-ADU-only permits in 2023. See our Seattle page.
- Boise: The city's pre-approved ADU plans are public domain, and "there cannot be a charge to provide these plans."
- Fresno: The city offers five pre-approved ADU plans, from a 340-square-foot studio to a 1,015-square-foot three-bedroom unit.
Fee waivers. Some cities waive fees for ADUs, such as Portland's SDC waiver above. California's HCD says "some local agencies are creating funding opportunities for ADU/JADU predevelopment and construction costs, or they are waiving fees." Colorado's ADU Grant Program funds certified local governments for pre-approved plans, technical help, and "waiving, reducing, or providing financial assistance for ADU-associated fees." Ask your city whether it offers any of these.
For loans and grants, see ADU financing. [13][16][17][24][25][30][31][32]
Estimate your own cost and rent payback
Use our ADU cost and rent payback calculator to plug in your own bids, fees and expected rent.
For a sense of rents in California, the 2021 statewide survey found "the median rental price of a new ADU in California is $2,000." It ranged "from $1,925 in the Central Coast region to $2,200 in the San Francisco Bay Area." Rents where you live may be very different. [1]
Questions people ask
How much does it cost to build an ADU?
It depends on where you build, the size and the type. The public studies we found are local: UC Berkeley's 2021 survey found a California median of $150,000 ($250 per square foot); Seattle's 2022 survey found a median of $200,000 ($100,000 attached, $230,000 detached); and Portland State's report on a 2017 survey found a median of $127,000 for detached units. These figures are several years old. Get local bids. [1][2][3]
Are small ADUs exempt from impact fees?
It depends on the state. In California, ADUs of 750 square feet of interior livable space or less (and junior ADUs of 500 or less) pay no impact fees; from January 1, 2027, a larger ADU on a lot with up to two ADUs pays only on the area above 750 square feet. Montana bars city impact fees, and county impact fees where the county has zoning, on ADUs of any size. Washington caps ADU impact fees at 50 percent of the fee for the main house in urban growth areas of cities and counties that plan under the Growth Management Act. Idaho (by February 1, 2027) and North Carolina (from January 15, 2027) bar covered cities from charging ADUs more than a similar single-family home, and Massachusetts bars impact fees for Protected Use ADUs that a single-family home wouldn't pay. Elsewhere, ask your city. [5][6][7][8][9][10][18][19][20][21][22]
Do I pay school fees on an ADU?
In California, school districts may charge school impact fees for ADUs larger than 500 square feet of interior livable space. ADUs and junior ADUs under 500 square feet are not subject to school impact fees. Outside California, ask your city which fees apply. [13]
Will I pay new utility connection fees for a garage conversion?
In California, usually not: a unit built within an existing house or accessory structure can't be required to get a new or separate utility connection or pay a related fee, unless it is built with a new single-family home or sold separately. In Massachusetts, a city or town can't require a separate utility connection for a Protected Use ADU, though a utility still can. Elsewhere it depends on your water and sewer provider, so ask before you design. [5][9]
What costs besides construction should I budget for?
California's housing finance agency lists ADU pre-development costs as site prep, architectural designs, permits, soil tests, impact fees, property surveys and energy reports. Also ask your water and sewer provider about connection fees or capacity charges. [4][13]
Sources (32)
- First Ever Statewide ADU Owner Survey Shows Growth, Room for Improvement, Terner Center for Housing Innovation, UC Berkeley. Accessed October 10, 2026.
- Accessory Dwelling Units 2022 Annual Report (March 2023), City of Seattle, Office of Planning and Community Development. Accessed October 10, 2026.
- The Portland ADU Market: Conditions, Costs, Drivers, Incentives (May 2019), Northwest Economic Research Center and Institute for Sustainable Solutions, Portland State University. Accessed October 10, 2026.
- ADU Grant, California Housing Finance Agency (CalHFA). Accessed October 10, 2026.
- Government Code Section 66311.5, California Legislative Information. Accessed October 10, 2026.
- RCW 36.70A.681 Accessory dwelling units — Limitations on local regulation, Washington State Legislature. Accessed October 10, 2026.
- Idaho Code 67-6541 Accessory dwelling units, Idaho State Legislature. Accessed October 10, 2026.
- 76-2-345. Accessory dwelling units -- regulations -- restrictions, MCA, Montana Legislature (Montana Code Annotated 2025). Accessed October 10, 2026.
- 760 CMR 71.00: Protected Use Accessory Dwelling Units, Executive Office of Housing and Livable Communities. Accessed October 10, 2026.
- Session Law 2026-59 (Senate Bill 445), Regulatory Reform Act of 2026, North Carolina General Assembly. Accessed October 10, 2026.
- Reaching California's ADU Potential: Progress to Date and the Need for ADU Finance, Terner Center for Housing Innovation and Center for Community Innovation, UC Berkeley. Accessed October 10, 2026.
- Remaining barriers to Accessory Dwelling Units (ADUs), Massachusetts Executive Office of Housing and Livable Communities. Accessed October 10, 2026.
- Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
- Boise City Impact Fee Schedule effective October 1, 2025, City of Boise. Accessed October 10, 2026.
- Accessory Dwelling Units (ADUs), City of Portland, Portland Permitting & Development. Accessed October 10, 2026.
- Pre-Approved ADU Plans, City of Boise Planning and Development Services. Accessed October 10, 2026.
- Accessory Dwelling Units (ADU), City of Phoenix Planning and Development Department. Accessed October 10, 2026.
- SB 1117 (2026), Accessory dwelling units and junior accessory dwelling units (chaptered text), California Legislative Information. Accessed October 10, 2026.
- SB 1117 (2026) bill status, California Legislative Information. Accessed October 10, 2026.
- Government Code Section 9600, California Legislative Information. Accessed October 10, 2026.
- RCW 36.70A.680 Accessory dwelling units — Local regulation, Washington State Legislature. Accessed October 10, 2026.
- 76-2-215. Accessory dwelling units -- regulations -- restrictions, MCA, Montana Legislature (Montana Code Annotated 2025). Accessed October 10, 2026.
- House Bill 24-1152, Concerning Increasing the Number of Accessory Dwelling Units (Signed Act), Colorado General Assembly. Accessed October 10, 2026.
- Accessory Dwelling Unit (ADU) Grant Program, Colorado Department of Local Affairs, Division of Local Government. Accessed October 10, 2026.
- Apply for an Accessory Dwelling Unit (ADU) System Development Charge (SDC) Waiver, City of Portland. Accessed October 10, 2026.
- Sewer Connection Charges Based on ERU Unit of $3,235.00, Effective January 1, 2026, City of Las Vegas, Building & Safety. Accessed October 10, 2026.
- New Construction Checklist for Single Family, 2 Family, Townhome and Accessory Dwelling Unit (ADU), City of Saint Paul, Department of Safety and Inspections. Accessed October 10, 2026.
- Accessory Dwelling Units and the Building Code, City of Saint Paul, Department of Safety and Inspections. Accessed October 10, 2026.
- Pre-Approved ADU Cost Estimator: ADU Permit, School, & Impact Fees & Construction Estimates (25.10.27), City of Fresno. Accessed October 10, 2026.
- ADU Program, City of Fresno Planning and Development Department. Accessed October 10, 2026.
- 9-461.20. Municipal housing; standard preapproved housing design plans; indemnification; definition, Arizona State Legislature. Accessed October 10, 2026.
- Accessory Dwelling Units 2023 Annual Report (July 2024), City of Seattle, Office of Planning and Community Development. Accessed October 10, 2026.