Building an ADU in Pleasanton

City code and California law · Last reviewed October 10, 2026

Pleasanton allows ADUs on single-family and multifamily lots. A "state-exempt" detached ADU of 800 square feet or less needs only 4-foot side and rear setbacks and skips the city's design and floor area rules. Larger ADUs can be up to 850 or 1,000 square feet but must match the main home and may need a parking space. There is no Planning review fee, and ADUs under 750 square feet pay no capital facilities or transportation fees. Call the Planning Division at (925) 931-5600 with questions. [1][2][3]

Pleasanton at a glance

ADUs allowed
Yes, on lots with an existing or proposed single-family or multifamily home in residential and some mixed-use, commercial and agricultural zones [1][2]
State-exempt detached ADU
Up to 800 sq ft, 16 to 20 ft tall depending on location, 4-ft side and rear setbacks [1][2]
Max size, other detached ADUs
850 sq ft for a studio or one bedroom 1,000 sq ft for two or more bedrooms [1][2]
Max size, attached ADU
50% of the home or 800 sq ft, whichever is greater, up to 850 or 1,000 sq ft Conversions can be larger [2]
Height
Detached: 16 ft (18 ft plus 2 ft for roof pitch near major transit). Attached: 25 ft [2]
Parking
One space for a non-exempt ADU unless an exemption applies None for JADUs; no replacement for garage parking converted to an ADU [1][2]
Impact fees
No capital facilities or transportation fee under 750 sq ft Reduced per-sq-ft fees from 750 sq ft [1][3]
Approval deadline
Approve or deny within 60 days of a complete application when a home already exists [2]
Preapproved plans
Yes 7-business-day review and a $1,000 flat plan review fee [4]
Short-term rental
No; rentals must be at least 30 days [2]
Selling an ADU separately
Not allowed, except under Gov. Code 66341 [2]
On this page
  1. At a glance
  2. What you can build in Pleasanton
  3. Size, height and setbacks
  4. Parking
  5. Fees
  6. How long it takes
  7. Garage conversions and junior ADUs
  8. Renting, selling and legalizing an ADU
  9. Where Pleasanton's rules and state law differ
  10. Permit steps
  11. Pre-approved plans
  12. Who to call
  13. Questions people ask

What you can build in Pleasanton

Pleasanton allows ADUs and junior ADUs in its R-1, RM, residential planned unit development (PUD), mixed-use, C-C and agricultural zones, on lots with an existing or proposed single-family or multifamily home. The rules are in Chapter 18.106 of the Municipal Code, last amended in October 2025. The city's ADU handout (May 2026) summarizes it.

The city splits ADUs into two groups:

On a single-family lot, the code allows one converted ADU, one new detached ADU of up to 800 sq ft and one junior ADU. The handout describes the same lot as allowing "an attached ADU, a detached ADU and one JADU." The code's JADU section says a lot with a JADU can have "only one other residential unit and up to one other accessory dwelling unit." HCD's handbook says that on a single-family lot, cities must allow at least one ADU made from existing space, one JADU and one new detached ADU. Ask the Planning Division which combination fits your lot.

On a multifamily lot, you can convert non-living space such as storage rooms, attics, basements or garages: at least one ADU, and up to 25% of the units in each building. You can also add up to eight detached ADUs with an existing multifamily building (no more than the number of homes on the lot), or up to two with a proposed one. [1][2][4][5]

Size, height and setbacks

Detached ADUs. A non-exempt detached ADU can be up to 850 sq ft for a studio or one bedroom, or 1,000 sq ft with two or more bedrooms. It needs 4-foot side and rear setbacks. The handout adds a 10-foot street-side setback if the ADU is over 800 sq ft. A detached ADU can be 16 feet tall. Within a half-mile walk of a major transit stop or high-quality transit corridor, it can be 18 feet plus 2 more feet for a roof pitch that matches the main home. On a lot with a multistory multifamily building, it can be 18 feet. A converted accessory building can keep its existing height and setbacks.

Attached ADUs. An attached ADU can be up to 50% of the main home's floor area or 800 sq ft, whichever is greater. The added floor area can't exceed 850 sq ft for a studio or one bedroom, or 1,000 sq ft with two or more bedrooms. Converted space can be larger. The code allows an attached ADU up to 25 feet tall and two stories. The handout lists 16 feet for an attached ADU, or 25 feet for one on a second story, so confirm the height with the Planning Division. Unless it qualifies as state-exempt, it follows the main home's front, side and rear setbacks.

Floor area and open space. An ADU over 800 sq ft must fit within your lot's floor area ratio and open space limits. These limits can't shrink a qualifying ADU below 800 sq ft. A non-exempt ADU also needs access to at least 80 sq ft of open space on the lot.

Design rules for non-exempt ADUs. The ADU must use the same wall material, trim, roof form, windows and railings as the main home. If it is less than 10 feet from a side or rear line, you need a solid fence at least 6 feet tall plus plants that grow at least 10 feet tall. Exterior lights must be shielded and pointed down. Balconies and upper-story decks are not allowed. Second-story windows within 25 feet of a property line need a sill at least 5 feet above the floor or frosted glass. An attached ADU's entry door must be on a different side of the house than the main door. [1][2]

Parking

A non-exempt ADU needs one extra off-street space. It can be tandem (for example, in the driveway) or in a setback, but not in the front setback unless it's on the driveway. No space is needed if the ADU is within half a mile of public transit, in a historic district, part of your existing home or an existing accessory building, in an area with on-street permits not offered to the ADU's occupant, or within one block of a car share vehicle. The code also exempts an ADU built with a new home on the same lot, if the ADU or lot meets the code's other criteria.

If you demolish or convert a garage, carport or parking structure to build an ADU, you don't have to replace those spaces. Junior ADUs need no parking of their own. But if a JADU removes required garage parking for the main home, the code says replacement spaces must go on the same lot. HCD's handbook says a city may not require parking for a JADU, even one converted from an attached garage. Confirm with the Planning Division. [1][2][5]

Fees

Pleasanton charges no fee for Planning review. You pay building permit and plan review fees from the city's Development Fee schedule. With a preapproved plan, the plan review fee is a flat $1,000, plus construction and inspection fees.

The city's Development Fees handout (February 1, 2026) lists these ADU impact fees:

Rates are higher for ADUs on multifamily lots. For every ADU, the fee is the lower of the per-square-foot ADU rate or a share of the main-home rate based on the ADU's size compared with the main home. Sewer connection fees for an ADU are $2.22 per sq ft to the city plus $9.75 per sq ft to the Dublin San Ramon Services District. A detached or other ADU not inside an existing building needs its own utility connection, with charges based on its size or number of plumbing fixtures.

State law, as HCD explains it, exempts ADUs of "750 square feet of interior livable space or less" from impact fees, so an ADU of exactly 750 sq ft shouldn't pay them. Confirm with the city before you pay. See our ADU cost guide. [1][2][3][4][5]

How long it takes

Pleasanton's code says the city will approve or deny an ADU or JADU application within 60 days of a complete application if there is already a home on the lot. If it denies one, it must send a full list of what is wrong and how to fix it. Applications with preapproved plans are reviewed in 7 business days, compared with 15 business days for standard applications. See our ADU permit process guide. [2][4]

Garage conversions and junior ADUs

You can convert a garage or shed into an ADU, and you don't have to replace garage parking you lose. A JADU in a garage is treated differently (see Parking). If you convert garage space, you can keep the garage door or fill it in to match the house. See our garage conversion guide.

A junior ADU (JADU) is 150 to 500 sq ft and fits entirely inside a single-family home, which can include an attached garage. It needs an efficiency kitchen with a sink, cooking appliance, counter and cabinets. It may share a bathroom with the home or have its own. The code says it needs its own separate interior and exterior entrances. Before the building permit is issued, you record a covenant with the Alameda County Recorder. You must also take part in the city's rent monitoring program if you rent it.

The handout says owner occupancy is required only when the JADU shares a bathroom with the home. That matches state law in 2026, as HCD explains it. The code's JADU rental rules and covenant text are still written around the owner living on the lot, so confirm with the Planning Division if your JADU has its own bathroom. [1][2][4][5]

Renting, selling and legalizing an ADU

ADUs must be rented for at least 30 days. A non-exempt ADU can't be sold or owned separately from the main home, except under Gov. Code 66341. If you rent out a non-exempt ADU, you must take part in the city's monitoring program on rent levels.

If you have an ADU or JADU built without permits before January 1, 2020, the city's ADU/JADU Amnesty and Legalization bulletin explains how to permit it. You submit a building permit application with as-built plans and a substandard building checklist. The city can require fixes only for unsafe, substandard conditions. No extra penalty fees apply. [2][6]

Where Pleasanton's rules and state law differ

We found no recent letter from the state housing agency HCD reviewing Pleasanton's ADU ordinance. A few local rules read differently from state law as HCD explains it:

Where a city rule is stricter than state law, ask the Planning Division how it applies. See our California ADU law overview. [1][2][3][5]

Permit steps in Pleasanton

  1. Check the rules for your lot

    Read the city's ADU handout and ADU page. Ask the Planning Division at pod@cityofpleasantonca.gov whether your design is state-exempt. [1][4]

  2. Choose a design

    Hire a designer, or contract with a designer whose plan is on the city's preapproved list. Preapproved plans still need site-specific plans, studies and engineering. [4]

  3. Prepare your plans

    Follow the Building and Safety Division's Residential Submittal Requirements. For a non-exempt ADU, show matching materials and colors on the elevations, as the code requires. [1][2]

  4. Apply online

    Create an account on Accela Citizen Access, select "Building", then "Create Application". The city says to choose "Addition" as the project type for an ADU or JADU. Upload your plans and documents. [4][7]

  5. Go through plan review and pay fees

    Staff check that your submittal is complete and email you if anything is missing. The city must approve or deny a complete application within 60 days when a home already exists. Pay plan review, permit and impact fees from the Development Fee schedule. [1][2][7]

  6. Record the JADU covenant, then build

    For a JADU, record the restrictive covenant with the Alameda County Recorder before the building permit is issued. Get a new street address for the ADU from the engineering department. [2]

Pre-approved and sample plans

Who to call

Questions people ask

How big can an ADU be in Pleasanton?

A state-exempt detached ADU can be up to 800 sq ft with 4-foot side and rear setbacks. Other detached ADUs can be up to 850 sq ft for a studio or one bedroom, or 1,000 sq ft with two or more bedrooms. Attached ADUs are limited to 50% of the home or 800 sq ft, whichever is greater, up to those same caps. Converted space can be larger. [1][2]

Does Pleasanton charge impact fees on ADUs?

ADUs under 750 sq ft pay no capital facilities or transportation development fee, and no ADU pays the affordable housing fee. From 750 sq ft, reduced per-square-foot fees apply. You still pay building permit, plan review and sewer connection fees. [1][3]

Do I need parking for an ADU in Pleasanton?

A non-exempt ADU needs one space unless it's within half a mile of public transit or meets another exemption. State-exempt ADUs and junior ADUs need none, and you don't have to replace a garage you convert. [1][2]

Can I build a two-story ADU in Pleasanton?

The code allows an attached ADU up to 25 feet and two stories, with privacy rules for second-story windows (the handout lists 16 feet unless the ADU is on a second story). A detached ADU is limited to 16 feet, or 18 feet plus 2 feet for roof pitch near major transit. [1][2]

Can I rent my Pleasanton ADU on Airbnb?

No. Pleasanton requires ADU rentals to be at least 30 days, and JADU rentals must be longer than 30 days. [2]

Sources (8)
  1. Accessory Dwelling Units and Junior Accessory Dwelling Units (May 2026), City of Pleasanton, Planning Division. Accessed October 10, 2026.
  2. Pleasanton Municipal Code, Chapter 18.106 Accessory and Junior Accessory Dwelling Units, City of Pleasanton (eCode360). Accessed October 10, 2026.
  3. Development Fees (February 1, 2026), City of Pleasanton, Community and Economic Development Department. Accessed October 10, 2026.
  4. Accessory Dwelling Units (ADUs), City of Pleasanton, Community and Economic Development. Accessed October 10, 2026.
  5. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
  6. ADU and JADU Amnesty and Legalization, City of Pleasanton, Building and Safety Division. Accessed October 10, 2026.
  7. Permits, Forms & Fees, City of Pleasanton, Community Development. Accessed October 10, 2026.
  8. ADU and JADU FAQs, City of Pleasanton, Building and Safety Division. Accessed October 10, 2026.