Building an ADU in the City of Davis

City code and California law · Last reviewed October 9, 2026

Yes, you can build an accessory dwelling unit (ADU) in the City of Davis on a lot zoned for homes. Davis updated its ADU code on September 1, 2026. ADUs that meet the state's standard combinations need only a building permit; other ADUs follow local standards, such as 850 sq ft (studio or one bedroom) or 1,000 sq ft (two or more bedrooms) for a detached unit. No parking is required, and ADUs under 750 sq ft pay no impact fees. [1][2]

Davis at a glance
ADUs allowedYes, on lots zoned for single-family or multifamily use with an existing or proposed home [1]
Which rules applyTwo ministerial paths: building-permit-only ADUs under state Gov. Code 66323, or one ADU under local standards; larger ADUs need an administrative use permit [1]
Detached ADU max size (local standards)850 sq ft (0-1 bedroom) or 1,000 sq ft (2+ bedrooms) of interior livable space; up to 1,200 sq ft with an administrative use permit [1]
Attached ADU max size50% of the home's gross floor area [1]
Junior ADUAllowed under state law: up to 500 sq ft inside the house [1][2]
Height (local standards)18 ft for a detached ADU (including 2 ft for roof pitch); attached: 25 ft or the zone limit, whichever is lower [1]
Side and rear setbacks4 ft for new ADUs; none for conversions of existing structures [1]
ParkingNone required; no replacement for a converted or demolished garage [1]
Impact feesNone under 750 sq ft of interior livable space; larger ADUs pay in proportion to the home's size [1][2]
Pre-designed plansFree city plans: 300 sq ft studio, 565 sq ft one-bedroom, 740 sq ft two-bedroom, in three styles [6]
Building permit processingTypically 20-35 business days, per the city (state law sets a 60-day approve-or-deny deadline) [2][4]
Short-term rentalBuilding-permit-only ADUs and junior ADUs must be rented for more than 30 days [1]
Owner occupancyNot required for an ADU; required for a junior ADU only if it shares a bathroom with the house [1][2]
On this page
  1. At a glance
  2. What you can build here
  3. Size, height and setbacks
  4. Parking
  5. Fees
  6. How long it takes
  7. Pre-designed and pre-approved plans
  8. Garage conversions and junior ADUs
  9. Renting or selling your ADU
  10. State review of Davis's ADU rules
  11. Permit steps
  12. Pre-approved plans
  13. Who to call
  14. Questions people ask

What you can build here

Davis's ADU rules are in Municipal Code Section 40.26.450. The city rewrote it with Ordinance 2693, dated September 1, 2026. The section says that where it conflicts with state law, "state law shall prevail."

The city's ADU webpage still says that "Since the last update to the City's ADU requirements in 2021, certain City zoning regulations in Chapter 40 may be different due to State updates to ADU laws." That note predates the September 2026 update, so rely on the current code and confirm with the city.

Davis has two ministerial (no-hearing) paths:

ADUs that meet neither path may be approved as "non-ministerial" ADUs with an administrative use permit, which requires the director to make findings.

Every ADU also needs a building permit. ADUs don't count toward the lot's density limit. For lot splits, see our SB 9 lot split guide. [1][2][3]

Size, height and setbacks

Local-standards ADUs:

Building-permit-only ADUs under Gov. Code 66323(a)(4) may be 18 ft tall plus 2 ft for roof pitch.

Non-ministerial ADUs (administrative use permit): up to 1,200 sq ft and 30 ft tall, with 5 ft interior side and 10 ft rear setbacks (3 ft next to an alley, park or greenbelt), 50% maximum lot coverage and 20% usable open space.

Design (local standards). The ADU must have the same roof pitch as the house, give or take 2/12, with matching eave details, and a separate exterior entrance. On historic or conservation-overlay properties it can't require changes to the street-facing facade, and ADUs that could affect a California Register property must follow the federal Secretary of the Interior's Standards.

Confirm the standards for your lot with Community Development at (530) 757-5610. [1][4]

Parking

Davis's code says: "No additional vehicle parking space is required for an ADU." That applies to non-ministerial ADUs too.

If you convert or demolish a garage, carport or covered parking to build an ADU, you don't have to replace those spaces as long as the ADU stays a legal ADU. State law also bars parking requirements for junior ADUs. [1][2]

Fees

The code says ADUs "that are less than seven hundred fifty square feet of interior livable space shall not be subject to impact fees," and larger ADUs "shall be charged impact fees that are proportional in relation to the square footage of the primary dwelling unit." State guidance says the exemption covers ADUs of "750 square feet of interior livable space or less," so ask the city before designing at exactly 750 sq ft.

Utility connections. An ADU may use the house's water and sewer connections. For a new ADU that isn't a conversion, the city may require a separate utility connection, with a connection fee or capacity charge proportionate to the ADU's burden.

Monthly bills. The city's Cost of Building an ADU handout says four charges on your utility bill go up once the ADU is finaled: the municipal service tax, public safety charge, sanitation and sewer. In the city's example the monthly bill rose by $59.06. Rates change, so check the city's current utility rates.

State guidance says school districts may charge ADUs over 500 sq ft, and ADUs under 500 sq ft of interior livable space are not subject to school impact fees. Building permit fees are set when staff process your application. See our ADU cost and ADU financing guides. [1][2][4][5]

How long it takes

The code says the director reviews and approves a complete ADU permit application ministerially, with no public hearing, within the timelines in state Gov. Code 66317.

For building permits, the city's Building Division says "Typical processing times vary between 20 and 35 business days from the date of submittal," and applications are reviewed in the order received.

State law says a city must tell you within 15 business days whether your application is complete, and must approve or deny a complete ADU application within 60 days when there is already a home on the lot. See our ADU permit process guide. [1][2][4]

Pre-designed and pre-approved plans

The city runs a program, under state law AB 1332, where designers can have ADU plans plan-checked by the city at their own cost. Once accepted as a "master plan," the designs are posted on the city's ADU webpage. The city says those posted plans are "for reference only" and are not construction drawings; owners can view the elevations and floor plans, and review time is shorter because the plans were already checked. Each project still needs site plan review by Planning before a building permit.

The city also offers free Pre-Designed ADU Plans in three sizes: a 300 sq ft studio, a 565 sq ft one-bedroom and a 740 sq ft two-bedroom, each in Adobe, Agrarian or Mid-Mod style. The city says they were plan-checked in advance, so review is quicker and plan check fees are reduced, but changes to the plans are not accepted. To get the official plan set, you submit a site plan and a signed Hold Harmless and Indemnification Agreement in person at Community Development. The city says a California licensed general contractor is required before the building permit is issued for these plans. [3][6]

Garage conversions and junior ADUs

You can convert a garage or other existing structure into an ADU. No new setback is required inside the existing structure, and you don't have to replace the lost parking. If a garage conversion goes through the non-ministerial (use permit) path, the garage door must be removed and replaced with walls, windows and trim that match the house. See our garage conversion guide.

A junior ADU (JADU) can be up to 500 sq ft inside a single-family home and is approved with a building permit only. Before the certificate of occupancy, you record a declaration of restrictions: the JADU can't be sold separately, can't be rented for less than 31 consecutive days, and, unless it has its own bathroom, the owner must live in the JADU or the house. That matches the state's 2026 rule. See our junior ADU guide.

Fire sprinklers. The code says ADUs and JADUs must have sprinklers if the house is required to have them. Building an ADU doesn't trigger sprinklers in an existing apartment building.

Guest houses are different: living space in an accessory building with no kitchen, which can't be rented as a separate home. [1][2][3]

Renting or selling your ADU

ADUs and JADUs approved with a building permit only "shall be rented only for terms longer than thirty days." Ask the city about rental rules for local-standards ADUs.

State law bars cities from requiring owners to live on a property because it has an ADU. An ADU can be sold separately from the house only under the state's nonprofit, affordable-housing exception (Gov. Code 66341), which the Davis code spells out.

The code also says the city won't deny an ADU because of a nonconforming zoning condition, building code violation or unpermitted structure on the lot that doesn't threaten health and safety. An ADU may raise your property taxes; see our ADU property tax guide. [1][2]

State review of Davis's ADU rules

On October 8, 2025, the state housing agency (HCD) sent Davis a letter of technical assistance. It said the most recent ADU ordinance HCD had on file for the city was from 2019 and "may be outdated and out of compliance with State ADU Law," and asked for a response by November 7, 2025.

The city's code shows ADU amendments in 2020 and 2021 and a rewrite by Ordinance 2693 on September 1, 2026. We did not find an HCD review of the 2026 ordinance. [1][7]

Permit steps in Davis

  1. Choose your path

    Decide whether your ADU fits the state's building-permit-only combinations or the city's local standards in Section 40.26.450. Ask Community Development at (530) 757-5610 if unsure. [1][4]

  2. Design the ADU

    Hire a designer or check the city's ADU webpage for plans already checked by the city. Planning reviews the site plan for each project. [3]

  3. Apply

    Download the building forms, then email the application and documents to OnlinePermits@cityofdavis.org. Owner-builders may apply. Staff contact you with timelines, any extra documents and fees. [4]

  4. Plan review

    Applications are reviewed in the order received, typically in 20-35 business days. [4]

  5. Pay fees and get the permit

    Fees of $1,000 or less can be paid online with your permit number; otherwise pay by check. For a junior ADU, record the declaration of restrictions before the certificate of occupancy. [1][4]

  6. Build and pass inspections

    Schedule inspections with the Building Division. Once the ADU is finaled, your city utility charges will increase. [4][5]

Pre-approved and sample plans

Who to call

Questions people ask

How big can an ADU be in Davis?

Under the local standards, a detached ADU can be 850 sq ft (zero or one bedroom) or 1,000 sq ft (two or more bedrooms), and an attached ADU up to 50% of the house. ADUs that meet the state's standard combinations can be approved with only a building permit, and an ADU of up to 1,200 sq ft is possible with an administrative use permit. [1]

Do I need parking for an ADU in Davis?

No. The code says no additional parking space is required for an ADU, and you don't have to replace a garage or carport you convert or demolish. [1]

Do ADUs pay impact fees in Davis?

Not if they are under 750 sq ft of interior livable space. Larger ADUs pay impact fees in proportion to the size of the house. A new detached ADU may also need its own utility connection with a proportional fee. [1]

How long does an ADU permit take in Davis?

The city says building permits typically take 20 to 35 business days from submittal. State law requires a decision on a complete ADU application within 60 days. [2][4]

Will my utility bill go up with an ADU in Davis?

Yes. The city says the municipal service tax, public safety charge, sanitation and sewer charges increase once the ADU is finaled. In its example, the monthly bill rose by $59.06. [5]

Sources (7)
  1. Davis Municipal Code Sections 40.26.450 (Accessory dwelling units and junior accessory dwelling units, Ord. 2693, 9/1/2026) and 40.26.460 (Non-ministerial ADUs), City of Davis (eCode360). Accessed October 9, 2026.
  2. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 9, 2026.
  3. Accessory Dwelling Units and Guest Houses, City of Davis Community Development and Sustainability. Accessed October 9, 2026.
  4. Building Division, City of Davis Community Development and Sustainability. Accessed October 9, 2026.
  5. Cost of Building an ADU, City of Davis. Accessed October 9, 2026.
  6. Pre-Designed ADU Plans, City of Davis Community Development and Sustainability. Accessed October 9, 2026.
  7. City of Davis, Accessory Dwelling Unit (ADU) Ordinance Updates, Letter of Technical Assistance (October 8, 2025), California Department of Housing and Community Development. Accessed October 9, 2026.