Building an ADU in Santa Ana
City code and California law · Last reviewed October 10, 2026
Santa Ana allows ADUs on any lot where homes are allowed, with no minimum lot size. A new attached or detached ADU can be up to 1,000 sq ft, detached ADUs can be two stories and 20 feet tall, and side and rear setbacks are 4 feet. The Planning Division reviews ADUs before building plan check, and the city offers pre-approved detached ADU plans that can be approved over the counter. A few city rules, such as the one-ADU limit on single-family lots and the owner-occupancy rule for junior ADUs, are stricter than state law as HCD describes it. [1][2][3][4][5]
Santa Ana at a glance
- Which rules apply
- Santa Ana Municipal Code sections 41-194 to 41-194.7 Last amended Feb. 2025 [1]
- ADU size
- 220 to 1,000 sq ft Attached ADUs also capped at 50% of the house (800 sq ft always allowed); 800 sq ft max if the lot also has a JADU [1]
- Setbacks
- 4 ft side, rear and street side Front same as the house; none for conversions [1]
- City planning fee
- $1,940 ADU review $594 over-the-counter review; $524 pre-approved plan review (FY 2026-27) [7]
- Approval deadline
- State law: completeness notice within 15 business days Decision within 60 days of a complete application [5]
- Short-term rental
- Not allowed ADUs and JADUs can be rented for 30 days or more [2]
On this page
Which rules apply in Santa Ana
Santa Ana's ADU rules are in section 41-194 and the sections after it of the zoning code. They were last amended by Ordinance NS-3076 in February 2025. The city's ADU/JADU Development Standards page summarizes them.
The city reviews ADUs ministerially: the executive director of the Planning and Building Agency approves or denies them based on whether the application is complete, meets the code, and the review fee has been paid. The code says applications that are incomplete or don't fully conform "will be rejected."
State law sets the floor for what any California city must allow; see our California page. Where the city's code is stricter than state law as the state housing agency (HCD) explains it, this page says so. Ask the Planning Division at (714) 647-5804 how those rules apply to your lot. [1][2][5]
What you can build
ADUs are allowed in all zones where homes or mixed-use development are allowed, including the R1, R2, R3 and R4 zones and specific plans that allow homes. Check your zone with the city's property information search. There's no minimum lot size.
- Single-family lot: the code allows no more than one ADU, plus one JADU. HCD's handbook says state law requires cities to allow one ADU converted from existing space, one JADU and one new detached ADU of up to 800 sq ft with 4-foot side and rear setbacks on the same lot. Ask Planning before you design around more than one ADU.
- Existing apartment building: ADUs converted from non-living space in the building (at least one, up to 25% of the units), plus up to eight detached ADUs, not more than the number of existing units. The city's example: a 12-unit complex can add eight detached and three converted ADUs, 11 in all.
- Lot with a proposed apartment building: up to two detached ADUs.
- No JADUs on lots with apartment buildings or with more than one detached house.
Size, height and setbacks
These standards come from Table 41-194.3 of the code.
- Size: at least 220 sq ft, up to 1,000 sq ft for an attached or detached ADU. An attached ADU also can't be more than 50% of the house's living space, except that an 800 sq ft attached ADU is always allowed. If the lot will have both an ADU and a JADU, the ADU is capped at 800 sq ft. Converting space inside the house or an existing accessory structure has no size limit, and an accessory structure can grow by up to 150 sq ft when converted.
- Height: a detached ADU can be two stories, up to 20 feet. An attached ADU can be as tall as the zone allows for the house. Conversions have no height limit.
- Setbacks: 4 feet from side, rear and street-side lot lines. The front setback matches the house, but an ADU of up to 800 sq ft can encroach into it. Conversions and same-size rebuilds of existing structures need no setback.
- Open space and spacing: single-family lots keep 1,200 sq ft of usable open space, a detached ADU must be 15 feet from the house, and an ADU 5 feet from other accessory buildings. These can all be reduced to fit an 800 sq ft ADU.
- Historic properties: ADUs and JADUs must meet the U.S. Secretary of the Interior's standards for historic properties.
HCD's handbook says a city's maximum size rules must allow an ADU of at least 850 sq ft (1,000 sq ft with more than one bedroom), and that a minimum size can't rule out an efficiency unit, which can be as small as 150 sq ft. The city's 50% cap on attached ADUs guarantees 800 sq ft, and its minimum is 220 sq ft. Confirm with Planning how these apply to your design. [1][3][5]
Parking and garage conversions
A newly built ADU needs one parking space, which can be tandem. No parking is required if the ADU is:
- within a half-mile walk of public transit,
- in a historic district,
- part of the house or an existing accessory structure,
- where on-street parking permits are required but not offered to the ADU occupant,
- within one block of a car-share vehicle,
- a studio with no bedroom, or
- applied for together with a new house or apartment building and meets one of the cases above.
A JADU needs no parking. If you convert or tear down a garage, carport or parking space to build an ADU, you don't have to replace that parking, and the demolition permit is issued along with the ADU permit. The city's FAQ page also says ADUs "must have pedestrian access from the street." See our garage conversion guide. [1][3]
Fees
The Planning Division's fee schedule for fiscal year 2026-27 lists:
- Accessory Dwelling Unit Review: $1,940
- ADU Over-the-Counter Review: $594
- ADU Pre-Approved Plan Review: $524
Some applications also carry a 7% technology fee, and card payments carry a 2.5% processing fee. Building permit, inspection, capacity and impact fees are paid before the permit is pulled. The city says to contact each department for current amounts. School district fees are paid separately at the school district office.
Under state law, an ADU with 750 sq ft of interior livable space or less pays no impact fees, and a larger one pays in proportion to the size of the house. ADUs and JADUs under 500 sq ft don't pay school impact fees. For typical building costs see our ADU cost guide. [2][4][5][7]
How long it takes
Planning reviews an ADU first, and then the plans go to Building Safety and Public Works for plan check. With a pre-approved plan, the city says an over-the-counter submittal "may be approved in as little as one day" if it is complete and meets the code. Standard ADUs on single-family lots outside historic areas can also get an over-the-counter Planning review, according to the city's submittal checklist.
State law sets the outside limits: the city must tell you in writing within 15 business days whether your application is complete, and approve or deny a complete application within 60 days when a home already exists on the lot. See our ADU permit process guide. [4][5][8]
Junior ADUs
A JADU is up to 500 sq ft, entirely inside a new or existing single-family home or its attached garage. It needs at least an efficiency kitchen and its own exterior entrance. It can have its own bathroom or share one with the house; if it shares, it needs interior access to the house. A JADU must meet the zone's standards for the house, such as setbacks, lot coverage and height, but needs no parking. The city requires a separate address for each ADU and JADU. See our junior ADU guide.
Owner occupancy. Before the building permit is issued, the city requires a recorded covenant saying the owner will live in either the house or the JADU. The covenant also bars selling the JADU separately and limits it to its approved size. Since 2026, state law requires owner occupancy only when the JADU shares bathroom facilities with the house. Ask Planning how the covenant applies to a JADU with its own bathroom. [1][2][3][5]
Renting it out and selling
You don't have to live on the property to have an ADU. ADUs and JADUs "may not be used as a short-term vacation rental, but can be rented for periods of 30 days or more."
An ADU can be sold separately from the house only if a qualified nonprofit built the house and the ADU under state law and the applicant signs an affordable housing agreement with the city.
If you live in an HOA, the city says to check with it, but "In general, HOAs cannot prohibit the construction of an ADU or JADU." HCD's handbook says state law voids HOA rules that effectively prohibit or unreasonably restrict ADUs and JADUs on lots zoned for single-family homes. [1][2][3][5]
Pre-approved plans and financing programs
Santa Ana's Pre-Approved ADU Plans are ready-made detached ADU plan sets you can download: studios and one-bedroom units in Ranch, Spanish, Traditional, Contemporary and Craftsman styles, and a two-bedroom Contemporary plan. You still need site-specific work, including a site plan and a grading permit exemption form.
To use them, your lot must have, or be planned for, a single-family home. It can't be in a flood zone (A or AE), a historic district (French Park, the Downtown Historic District or Floral Park) or Heninger Park. Pre-approved plan applications are submitted in person on paper, by appointment.
The city's FAQ page also links two financing programs, but check their status first. CalHFA's ADU Grant Program page says "The latest round of ADU funding has been fully allocated." The Orange County Housing Finance Trust says its board voted on May 21, 2025 "to discontinue further efforts to establish the Affordable ADU Loan Program." See our ADU financing guide. [3][4][9][10][11]
Permit steps in Santa Ana
Check your zone
Use the city's property information search to confirm your lot is in a zone that allows homes, and whether it's in a historic district or flood zone. [4][6]
Choose a standard design or a pre-approved plan
For a custom ADU, use the ADU/JADU submittal checklist and call Planning at (714) 647-5804 for submittal instructions. For a pre-approved plan, email planning@santa-ana.org for a pre-submittal consultation. [4][8]
Prepare your package
Include the signed application, dimensioned plans, the development standards compliance form and a grant deed (pre-approved plans also need a title report from the last six months). Pay the ADU Planning review fee. [4][8]
Submit to Planning
Detached ADUs on single-family lots and ADU conversions can go through the city's E-Plan system with the ADU application included. Pre-approved plans are submitted over the counter on paper. [4][12]
Get Building Safety and Public Works approval
After Planning approves, the plans go to Building Safety and Public Works for plan check. Call Building Safety at (714) 647-5800 and Public Works at (714) 647-5690 for their requirements. [4][8]
Record the JADU covenant and pay fees
For a JADU, record the owner-occupancy covenant on the city's template. Pay permit, inspection, capacity and impact fees, and pay school fees at the school district office. [1][4][8]
Pull permits and schedule inspections
Bring the city and school district clearances to pull permits, then call (714) 667-2738 to schedule inspections. [4]
Pre-approved and sample plans
Downloadable detached ADU plan sets (studio, one-bedroom and two-bedroom) for single-family lots outside flood zones and historic districts. [4][9]
Who to call
-
ADU review, submittal instructions and pre-submittal consultations (Planning@santa-ana.org)
20 Civic Center Plaza, Santa Ana, CA 92701
-
Santa Ana Building Safety Division
Building plan check requirements
-
Santa Ana Public Works Agency
Public Works plan check requirements
-
Santa Ana building inspections
Schedule inspections once permits are issued
Questions people ask
How big can an ADU be in Santa Ana?
Up to 1,000 sq ft for a new attached or detached ADU, with attached units also limited to 50% of the house (800 sq ft is always allowed). If you also build a JADU, the ADU is capped at 800 sq ft. A JADU can be up to 500 sq ft. [1]
Can I build a two-story ADU in Santa Ana?
Yes. A detached ADU can be up to two stories and 20 feet tall. An attached ADU can be as tall as the zone allows for the house. [1][3]
Do I need parking for an ADU in Santa Ana?
One space for a newly built ADU, unless an exemption applies, such as being within a half-mile walk of public transit or being a studio. JADUs and conversions need no parking, and you don't have to replace a converted garage. [1][3]
Does Santa Ana have pre-approved ADU plans?
Yes. The city offers downloadable detached ADU plan sets (studio, one-bedroom and two-bedroom) for single-family lots outside flood zones and historic districts. A complete over-the-counter submittal can be approved in as little as one day. [4][9]
Can I Airbnb my ADU in Santa Ana?
No. ADUs and JADUs can't be short-term vacation rentals; rentals must be for 30 days or more. [2]
Sources (12)
- Santa Ana Municipal Code Sec. 41-194 to 41-194.7, Accessory dwelling units (Supp. 33, Update 1), City of Santa Ana (Municode). Accessed October 10, 2026.
- ADU/ JADU Development Standards, City of Santa Ana Planning Division. Accessed October 10, 2026.
- Accessory Dwelling Unit (ADU) FAQs and Helpful Links, City of Santa Ana Planning Division. Accessed October 10, 2026.
- Pre-Approved ADU Plan Submittal Process, City of Santa Ana Planning Division. Accessed October 10, 2026.
- Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 10, 2026.
- Accessory Dwelling Units, City of Santa Ana Planning Division. Accessed October 10, 2026.
- Planning Division Fiscal Year 2026-2027 Fee Schedule, City of Santa Ana Planning Division. Accessed October 10, 2026.
- Accessory Dwelling Unit (ADU) & Junior ADU Submittal Checklist, Planning Application and Code Compliance Form, City of Santa Ana Planning and Building Agency. Accessed October 10, 2026.
- Pre-Approved ADU Plans, City of Santa Ana Planning Division. Accessed October 10, 2026.
- ADU Grant Program, California Housing Finance Agency. Accessed October 10, 2026.
- Affordable ADU Loan Program, Orange County Housing Finance Trust. Accessed October 10, 2026.
- Planning and Building Agency Electronic Plan (E-Plan) Review, City of Santa Ana Planning and Building Agency. Accessed October 10, 2026.