Building an ADU in the City of Sacramento

City code and California law · Last reviewed October 9, 2026

Yes, you can build an accessory dwelling unit (ADU) on a lot in the City of Sacramento that has a home on it. The city makes you pick one of two rulebooks: its own local ADU ordinance (up to two ADUs, detached ADUs up to 1,200 sq ft combined) or the state ADU standards (for example, one detached ADU up to 800 sq ft plus a conversion and a junior ADU on a single-family lot). The city offers free shelf-ready plans for detached ADUs, and its fee estimate shows no development impact fees on an ADU of 749 sq ft or less. [1][2][3][4][5]

Sacramento at a glance
ADUs allowedYes, on lots with an existing home (or one built at the same time); the city's local ordinance allows up to two ADUs per lot [1][2][6]
Which rules applyYou choose either the local ADU ordinance (City Code 17.228.105(B)) or the state ADU standards (17.228.105(C)); no mixing [2][6]
Detached ADU max size1,200 sq ft combined under the local ordinance; 800 sq ft under the state standards [2]
Attached ADU max size (local ordinance)50% of the existing home, or 850 sq ft (studio/1 bedroom) or 1,000 sq ft (2+ bedrooms), whichever is greater [2][6]
Junior ADUUp to 500 sq ft, inside the walls of a single-family home (including an attached garage) [1][6]
HeightLocal ordinance: the zone's height limit (35 ft in R-1). State standards: 18 ft, plus 2 ft to match the home's roof pitch [2]
Side and rear setbacksLocal ordinance: 3 ft, or the zone's setback if smaller (none for the first floor if the whole ADU is more than 60 ft from the front lot line). State standards: 4 ft [2][6][8]
ParkingNo minimum off-street parking; the 2040 General Plan (February 2024) ended parking mandates citywide [9]
Impact feesWaived for ADUs of 749 sq ft or less, per the city; state guidance says 750 sq ft or less [4][5][7]
Estimated city permit feesAbout $5,272 (749 sq ft), $10,624 (750 sq ft), $14,843 (1,200 sq ft), not counting school, sewer and sanitation fees [5]
Free pre-approved plansYes: studio (367 sq ft), one-bedroom (559 sq ft) and two-bedroom (747 sq ft) shelf-ready plans [3]
Plan review timeRoughly 1.5-2 months, per the city (state law sets a 60-day approve-or-deny deadline for a complete application) [7][13]
Short-term rentalNot allowed for ADUs built under the state standards (rentals must be 30 days or more); local-ordinance ADUs may be rented for less than 30 days only as City Code 17.228.104 allows [2][8]
Owner occupancyNot required for an ADU; required for a junior ADU that shares a bathroom with the main home [6][7]
On this page
  1. At a glance
  2. What you can build here
  3. Size, height and setbacks
  4. Parking
  5. Fees
  6. How long it takes
  7. Free shelf-ready ADU plans
  8. Garage conversions and junior ADUs
  9. Renting out your ADU
  10. Permit steps
  11. Pre-approved plans
  12. Who to call
  13. Questions people ask

What you can build here

An ADU is a permanent home on the same lot as your house. It can be detached, attached, made from a garage or other existing space, built above a garage, or a modular unit. All ADUs must meet California's building code (Title 24).

Sacramento gives you two sets of zoning rules, and you must pick one for the ADUs on your lot. There is "no pick/choose or mix/match of local and state standards." The city's ADU Resource Center has a side-by-side table.

Lots in the EA-2 or EA-3 overlay zone may have only one ADU. To check your zoning, overlays and whether your lot is in a historic district, use the city's Land Information Lookup App.

ADUs are allowed in Sacramento's 31 historic districts and on landmark properties. If you build under the local ordinance there, you must also meet the city's ADU Design Standards for Historic Properties.

Tiny homes on wheels do not count. The city says all homes must be on a permanent foundation and "Homes on wheels are currently not permitted."

State law also lets many single-family lots be split under SB 9. See our SB 9 lot split guide and the California page for the statewide rules. [1][2][6][7]

Size, height and setbacks

Under the local ordinance:

Under the state standards (single-family lot):

Converting an existing structure in its same footprint needs no new setback. Exact setbacks depend on your lot, so confirm with the Planning Division. [2][6][8]

Parking

Sacramento does not require off-street parking for new homes, including ADUs. The city says its 2040 General Plan, adopted in February 2024, "ended off-street minimum vehicle parking mandates for all properties in the city."

State law backs this up for ADUs. A city may not make you replace garage, carport or driveway parking that you remove or convert to build an ADU, and it may not require parking for a junior ADU.

Some objective design standards still apply to how you lay out any parking you choose to build. For example, the local-ordinance checklist bars new curb cuts on lots that don't front an alley. See the ADU application checklist (CDD-0009). [6][7][9]

Fees

The city's ADU fee estimate (CDD-0419), revised July 12, 2026, gives these approximate totals for a new detached ADU:

The jump at 750 sq ft is mostly impact fees (park, flood control and transportation). The city says that "Per State law, if the ADU is equal to or less than 749 square feet, the development impact fees are waived." State housing agency guidance says the exemption covers an ADU with "750 square feet of interior livable space or less," so a unit of exactly 750 sq ft may also qualify. Ask the city before you design right at that line.

The totals leave out several fees:

The optional Planning zoning review (form CDD-0009) is free starting July 12, 2026.

Help with costs. The city runs a program that cuts eligible impact fees by up to $10,000 per unit for deed-restricted affordable homes, while yearly funds last. See Reduction of Development Impact Fees for Affordable Housing. Units must stay affordable for at least 30 years. The city's budget page still lists the CalHFA ADU grant, but CalHFA says its latest round "has been fully allocated" (December 28, 2023). For other options see our ADU cost and ADU financing guides. [4][5][6][7][10][11][12]

How long it takes

You need a building permit for every ADU. You don't need a separate planning approval before you apply for it.

The city's posted timeline:

These times don't count the time you take to answer corrections. Every ADU also needs a new address, which can take up to four weeks to get.

State law says a city must approve or deny a complete ADU application within 60 days when there is already a home on the lot. If it denies the application, it must send a written list of what is wrong and how to fix it. Our ADU permit process guide explains this in more detail. [7][13]

Free shelf-ready ADU plans

The city offers free Shelf Ready ADU Plans for detached ADUs. Any resident can use them. They are all-electric.

You must add a site plan that shows where the ADU goes on your lot. "Modifications to the Shelf Ready Plans are not allowed, although mirroring of the plans is allowed." The city's submittal guide says each model has a left-side wall option that can sit as close as 1 ft to the property line. All other sides must be at least 5 ft from property lines. The two-bedroom model also needs solar (PV) plans.

When you apply for the building permit with a shelf-ready plan, you also file a hold harmless agreement (CDD-0439) and an owner certification (CDD-0438).

Check the code edition. The city says these plans meet the "2022 Residential Building Code." The 2025 California Building Standards Code took effect January 1, 2026. The city's rules for privately designed pre-approved plans say they are valid only within the code cycle they were approved for. Before you rely on a shelf-ready plan, ask the Building Division whether it has been updated for the 2025 code.

The city also runs a pre-approved ADU program for designers' plans, under state law AB 1332. Those plans are for detached ADUs only. They still need site-specific review, including zoning, before a permit is issued. On October 9, 2026 that page listed no designer plans and pointed to the shelf-ready plans. [3][14][15][16][17]

Garage conversions and junior ADUs

You can turn an existing garage into an ADU, or build an ADU above it. Under the local ordinance, a converted existing structure needs no setback if it keeps the same location and size. Under the state standards, a conversion must stay inside the existing structure, plus up to 150 sq ft added for entry and exit. Its side and rear setbacks are set in building review but are "not more than 4 feet." State law bars the city from making you replace the parking you lose. See our garage conversion guide.

A junior ADU (JADU) is up to 500 sq ft and sits entirely inside a single-family home, which can include an attached garage. It needs its own efficiency kitchen and a separate entrance. It may share a bathroom with the house; if it does, it also needs an inside door into the house.

A deed restriction must be recorded before the final building inspection. It must say the JADU can't be sold apart from the house. If the JADU shares bathroom facilities with the house, the owner must live in the house or the JADU. (The local-ordinance section of City Code 17.228.105 still says the owner must live on site for any JADU, but the city's 2026 CDD-0009 checklist and state law, as HCD describes it, require it only when the bathroom is shared. Confirm with the Planning Division.) If you rent out a JADU, the term must be longer than 30 days. See our junior ADU guide. [1][2][6][7][8]

Renting out your ADU

ADUs built under the state standards cannot be rented for less than 30 days. For ADUs built under the local ordinance, City Code 17.228.105 says they may be rented for less than 30 days only as allowed by City Code 17.228.104, titled "Bed and breakfast inn in residential zones." Ask the Planning Division before you plan short stays.

The city cannot require you to live on the property because you have an ADU. The only exception is an ADU sold separately to a qualified buyer under a special state law. Junior ADUs are different (see above).

An ADU may raise your property taxes. The city suggests asking the Sacramento County Assessor. The city's landlord and tenant resources page covers renting to tenants. [2][7][8][18]

Permit steps in Sacramento

  1. Check if an ADU is allowed on your lot

    Look up your zoning, overlays (EA-2 and EA-3 allow only one ADU) and historic status in the city's Land Information Lookup App. The ADU Resource Center's Step 1 explains the options. [2]

  2. Pick the local ordinance or the state standards

    Choose one set of rules for every ADU on the lot; you can't mix them. The local ordinance allows bigger and taller ADUs. The state standards allow a third unit on single-family lots. [2][6]

  3. Design the ADU or choose a free shelf-ready plan

    Draw a to-scale site plan that shows property lines, all structures and the distances between them. Then hire a designer or use a city shelf-ready plan. [3][19]

  4. Optional: get a free zoning review

    Submit the ADU Optional Zoning Review Application (CDD-0009) online to check zoning before you pay for full construction drawings. It is free starting July 12, 2026, and the city says it takes 1-3 weeks. [6][13]

  5. Apply for the building permit online

    Upload PDF plans and forms (including the CDD-0200 building permit application) through the city's Public Permit Portal. Paper plans are not accepted. The city routes your plans to other departments for review. [13][14][20]

  6. Request a new address and check for tree permits

    Every ADU needs a new address, which can take up to four weeks (see City Addressing). City Code requires a tree permit before removing certain trees, so check whether your project affects any. [6][13]

  7. Pay fees and pick up the permit

    Pay the remaining permit and impact fees when you pick up the permit. Pay school fees at the school district and bring the receipt to the city. [4][5]

  8. Build and pass inspections

    Inspections run from site preparation and foundation through framing, insulation and final inspections. You can move in after all final inspections pass. Schedule inspections through Building Permit Inspections. [21]

Pre-approved and sample plans

Who to call

Questions people ask

Does Sacramento have free ADU plans?

Yes. The city offers free, all-electric shelf-ready plans for detached ADUs: a studio (367 sq ft), a one-bedroom (559 sq ft) and a two-bedroom (747 sq ft). You add a site plan. You can mirror a plan, but you can't change it. The plans were drawn to the 2022 building code, so ask the Building Division whether they have been updated for the 2025 code. [3][17]

How much are ADU permit fees in Sacramento?

The city's fee estimate shows about $5,272 for a 749 sq ft ADU, $10,624 for 750 sq ft and $14,843 for 1,200 sq ft. That does not include school fees, regional sanitation or sewer development fees. Impact fees are waived for ADUs of 749 sq ft or less. [4][5]

Do I need a parking space for an ADU in Sacramento?

No. The city's 2040 General Plan, adopted in February 2024, ended minimum off-street parking requirements for all properties in the city. State law also says you don't have to replace a garage or driveway space you convert or demolish to build an ADU. [7][9]

How long does it take to get an ADU permit in Sacramento?

The city estimates roughly 1.5-2 months for building plan review, plus the time you take to answer corrections. The optional zoning review takes 1-3 weeks, and a new address can take up to four weeks. State law gives the city 60 days to approve or deny a complete application. [7][13]

Can I rent my Sacramento ADU on Airbnb?

Not if you build it under the state ADU standards; those ADUs cannot be rented for less than 30 days. ADUs built under the city's local ordinance may be rented for less than 30 days only as City Code 17.228.104 (the bed-and-breakfast inn rules) allows. A junior ADU can only be rented for terms longer than 30 days. Confirm with the Planning Division before you list. [2][7][8]

Can I put a tiny house on wheels in my backyard in Sacramento?

No. The city says all homes must be on a permanent foundation and "Homes on wheels are currently not permitted." Modular or pre-built ADUs set on a foundation are allowed. [1]

Sources (22)
  1. About ADUs, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  2. Step 1: Is An ADU Allowed On My Property?, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  3. Shelf Ready ADU Plans, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  4. Step 4: Costs, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  5. Accessory Dwelling Unit (ADU) Fee Estimate (New Construction), CDD-0419, revised 07-12-2026, City of Sacramento Community Development Department. Accessed October 9, 2026.
  6. Accessory Dwelling Unit (ADU) Optional Zoning Review Application, CDD-0009 (06/23/2026), City of Sacramento Community Development Department. Accessed October 9, 2026.
  7. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 9, 2026.
  8. Sacramento City Code 17.228.105 Accessory dwelling units and junior accessory dwelling units, City of Sacramento (American Legal Publishing). Accessed October 9, 2026.
  9. Parking Revisions, City of Sacramento Community Development Department. Accessed October 9, 2026.
  10. Reduction of Development Impact Fees for Affordable Housing, City of Sacramento Community Development Department. Accessed October 9, 2026.
  11. Step 4 Continued: Budget, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  12. ADU Grant Program, California Housing Finance Agency (CalHFA). Accessed October 9, 2026.
  13. Step 5: Development Application Submittal, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  14. Shelf Ready Accessory Dwelling Unit Plan Submittal Guide, City of Sacramento. Accessed October 9, 2026.
  15. Preapproved Accessory Dwelling Units (AB-1332), City of Sacramento Community Development Department, Building Division. Accessed October 9, 2026.
  16. Information for Designers (Preapproved ADUs), City of Sacramento Community Development Department, Building Division. Accessed October 9, 2026.
  17. Codes (California Building Standards Code), California Building Standards Commission. Accessed October 9, 2026.
  18. Step 7: Move In and Operate Your ADU, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  19. Step 3: Site Plan and Design, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  20. Appointments (Public Counter), City of Sacramento Community Development Department. Accessed October 9, 2026.
  21. Step 6: Construction and Inspections, City of Sacramento ADU Resource Center. Accessed October 9, 2026.
  22. Welcome to the City of Sacramento's Accessory Dwelling Unit (ADU) Resource Center, City of Sacramento. Accessed October 9, 2026.