Building an ADU in Redwood City

City code and California law · Last reviewed October 9, 2026

Redwood City now follows California's ADU law directly. In July 2026 it repealed its own ADU chapter, and its zoning code points to Government Code 66310 and following. A single-family lot can have one detached ADU, one converted ADU and one junior ADU. No parking is required. You apply online through eTrakIt with the city's ADU Completeness Checklist. Questions go to the Planning Division at (650) 780-7234. [1][2][3][4]

Redwood City at a glance
ADUs allowedYes, in all residential and mixed-use zones, with limited exceptions [1][3]
Units on a single-family lot1 detached ADU + 1 converted ADU + 1 JADU [3]
Max size, detached ADU850 sq ft (studio or 1 bedroom); 1,200 sq ft (2+ bedrooms), per the city's August 2026 handout [3]
Max size, attached ADU50% of the existing home [3]
Height, detached ADU16 ft; 18 ft (plus 2 ft for roof pitch) within a half mile of a major transit stop; 18 ft on multifamily lots [3]
Side and rear setbacks4 ft for new construction; conversions keep the existing setbacks [3]
ParkingNo new off-street parking required [3][4]
Base permit fee estimate$3,999.53 (up to 400 sq ft or garage conversion) to $5,321.71 (601-800 sq ft), plus valuation-based fees [4]
Impact feesNone for ADUs of 750 sq ft or less; school district fees may apply [4][5]
Pre-reviewed plansYes; city pre-review program (30-day review) and free HEART GLADUR plans [4]
Owner occupancyNot required for ADUs; required for a JADU that shares a bathroom [3]
Short-term rentalProhibited (rentals under 30 days) for ADUs and JADUs [3]
On this page
  1. At a glance
  2. Redwood City now uses state ADU law
  3. What you can build
  4. Size, height and setbacks
  5. Parking
  6. Fees
  7. Fire safety and the fire flow test
  8. Garage conversions and junior ADUs
  9. Renting and the ADU survey
  10. Lot splits and duplexes (SB 9)
  11. Permit steps
  12. Pre-approved plans
  13. Who to call
  14. Questions people ask

Redwood City now uses state ADU law

Redwood City used to have its own ADU rules in Article 37 of the Zoning Code. Ordinance 1130-892, adopted July 27, 2026, repealed Article 37. The zoning code now lists ADUs as a permitted accessory use under "Government Code Sections 66310 through 66339.5, as they may be amended from time to time."

The city's ADU handout, effective August 2026, sums up the key Planning and Building rules. It tells readers to see Government Code 66310 to 66342 for the full law. This page follows that handout. The city's ADU web page still lists some older figures (for example, a detached ADU of up to 1,000 sq ft), so confirm sizes with the Planning Division. For background on the state rules, see our California ADU law overview. [1][2][3][4]

What you can build

ADUs are allowed in all residential and mixed-use zones, "with limited exceptions, such as traffic flow, water, sewer, or public safety."

Every ADU must have a real kitchen. The city says that means "a stove/oven, 2-20 amp circuits, a sink and a food preserving appliance." Wet bars with countertop ovens don't count. The ADU's main entrance must be a side-hinged door, not a garage or patio door. [3][4]

Size, height and setbacks

Per the city's August 2026 handout:

Lot coverage, pervious area, open space and accessory structure rules of your zone still apply. But the city says "these restrictions cannot prevent you from building an 800 square foot ADU."

HCD, the state housing agency, says that where a city doesn't have its own compliant ADU ordinance, state law caps a new detached ADU at 1,200 sq ft and an attached ADU at 50% of the main home (at least 800 sq ft). The handout's 850 sq ft limit for a detached studio or one-bedroom ADU is lower than that 1,200 sq ft figure, and the city's ADU web page lists still other numbers (850 sq ft for one bedroom and 1,000 sq ft for more). The sources don't agree, so confirm the size limit with the Planning Division before you design. [3][4][5]

Parking

Redwood City requires no new off-street parking for an ADU or JADU. The city's ADU page says "no additional parking is required" for a detached ADU in single-family areas. State law also says a city can't require you to replace a garage or carport you convert or tear down to build an ADU. [3][4][5]

Fees

The city publishes these base fee estimates for a new ADU:

The city says these are estimates and "additional fees will be applied based on construction valuation," plus administrative, maintenance and other fees. See the city's Master Fee Schedule for all fees. A new address also carries an address fee, and fire flow requests have a fee.

The city says it charges no impact fees on ADUs under 750 sq ft. State law sets the cutoff at 750 sq ft or less, with proportional fees above that. The city must report each ADU to the school district, which decides on its own whether to charge school impact fees. HCD says school districts may charge fees on ADUs larger than 500 sq ft. For cost ranges, see our ADU cost guide. [3][4][5][6]

Fire safety and the fire flow test

For a new detached ADU, you need a fire flow test with your permit application to show there is enough water for firefighting. Request it through the city's Fire Flow Information Request page. The city says to allow about 20 business days, and that reports "may take up to 6 weeks." Start early.

Other fire and building rules from the handout and checklist:

[3][4][6][7]

Garage conversions and junior ADUs

Converting a garage is one of the most common ADU routes. A converted structure keeps its existing setbacks, and the city's lowest base fee estimate applies to a garage conversion. A garage door can't serve as the ADU's main entrance, and the replacement wall must match the house in color and materials. See our garage conversion guide.

A junior ADU can be up to 500 sq ft, inside a single-family home on an R-1 or RH lot. You may add up to 150 sq ft for an entrance. A JADU can share a bathroom with the main home; if it does, it needs inside access to the house and the owner must live in the JADU or the main home. [3][4]

Renting and the ADU survey

Owner occupancy is not required for an ADU. Short-term rentals of less than 30 days are prohibited for ADUs and JADUs.

Before the city will final your building permit, you must complete a short ADU Homeowner Survey about how the unit will be used and its expected rent. Send the email confirmation to the Building Department at permits@redwoodcity.org. [3][4]

Lot splits and duplexes (SB 9)

Redwood City applies SB 9 in its single-family zones through Zoning Code Section 5.10. On a lot that hasn't been split, you can build an SB 9 project and also apply for ADUs. On a lot created by an urban lot split, you can have up to two units in total, counting ADUs and JADUs. SB 9 homes need 4-foot side and rear setbacks and follow the zone's height limit. An SB 9 project can't demolish or alter housing rented by a tenant in the last three years, and it isn't allowed on some sites, such as historic properties and certain hazard areas. See our SB 9 lot split guide. [8]

Permit steps in Redwood City

  1. Get early advice

    Book a Zoom appointment with Planning staff through the city's online booking page, or call (650) 780-7234. The San Mateo County ADU Resource Center also offers one-on-one feasibility consults. [4]

  2. Request a fire flow test early (new detached ADUs)

    Submit a request through the city's Fire Flow Information Request page. Reports can take up to six weeks. [4][6]

  3. Prepare plans or choose pre-reviewed plans

    Hire a designer, or use free HEART GLADUR plans that the city has pre-reviewed. Pre-reviewed plans still need a site plan, foundation and utility details for your lot. [4]

  4. Complete the ADU Completeness Checklist

    Fill out the ADU Completeness Checklist. ADUs need their own application, plan set and permit number. The city says incomplete applications "will not be accepted and will not be subject to State shot clock guidelines." State law still requires the city to tell you within 15 business days whether your application is complete. [5][7]

  5. Apply online through eTrakIt

    Upload your plans, building permit application and checklist on eTrakIt. [4]

  6. Get an address and build

    The ADU needs its own address (the checklist says before the rough framing inspection) and an address fee applies. Projects valued over $50,000 must file a construction and demolition recycling form. [3][4][7]

  7. Complete the ADU survey and final the permit

    Complete the ADU Homeowner Survey and email the confirmation to permits@redwoodcity.org to finalize the building permit. [4]

Pre-approved and sample plans

Who to call

Questions people ask

How big can an ADU be in Redwood City?

The city's August 2026 handout lists 850 sq ft for a detached studio or one-bedroom ADU and 1,200 sq ft with two or more bedrooms. An attached ADU can be up to 50% of the existing home. The minimum is 150 sq ft. The city's web page shows other numbers, and HCD says that where a city has no ADU ordinance of its own, state law allows a detached ADU of up to 1,200 sq ft. Confirm the limit with the Planning Division. [3][4][5]

Does Redwood City have its own ADU ordinance?

Not anymore. The city repealed Article 37 of its Zoning Code in July 2026. ADUs are now allowed under the state ADU law, Government Code 66310 and following. [1][2]

Do I need parking for an ADU in Redwood City?

No. No new off-street parking is required for an ADU or JADU. [3]

How much does an ADU permit cost in Redwood City?

The city's base fee estimates run from $3,999.53 (up to 400 sq ft or a garage conversion) to $5,321.71 (601 to 800 sq ft), plus fees based on construction value. ADUs under 750 sq ft pay no impact fees, but the school district may charge its own fee. [4]

Are there free ADU plans in Redwood City?

Yes. The city has pre-reviewed free detached ADU plans from HEART of San Mateo County, from 400 to 800 sq ft. You still need site-specific plans and a permit. [4]

Can I rent my Redwood City ADU on Airbnb?

No. Rentals under 30 days are prohibited for ADUs and JADUs. [3]

Sources (8)
  1. Redwood City Zoning Code 4.2 (Use Regulations in Residential Zoning Districts), City of Redwood City (Municode). Accessed October 9, 2026.
  2. Redwood City Zoning Code, Code Comparative Table and Disposition List (Supp. No. 30), City of Redwood City (Municode). Accessed October 9, 2026.
  3. Accessory Dwelling Units (ADUs), Effective August 2026, City of Redwood City, Planning Division. Accessed October 9, 2026.
  4. Accessory Dwelling Unit Ordinance, City of Redwood City, Planning Division. Accessed October 9, 2026.
  5. Accessory Dwelling Unit Handbook (March 2026), California Department of Housing and Community Development. Accessed October 9, 2026.
  6. Fire Flow Information Request, City of Redwood City, Engineering. Accessed October 9, 2026.
  7. Accessory Dwelling Unit (ADU) Completeness Checklist (Rev 0 8/26), City of Redwood City. Accessed October 9, 2026.
  8. Redwood City Zoning Code 5.10 (SB 9 Projects), City of Redwood City (Municode). Accessed October 9, 2026.