Building an ADU in Bend, Oregon
City code and Oregon law · Last reviewed October 9, 2026
Bend allows up to two accessory dwelling units (ADUs) on a lot with a single-unit home. Under the development code, one ADU can be up to 800 square feet and a second ADU up to 500 square feet. You apply for one permit that covers both planning and building review, and the city estimates 4 to 8 weeks for processing. Bend also offers five free pre-approved plans. [1][2][3]
| ADUs per lot | Up to two, on a lot with a single-unit home (one in small dwelling unit developments; none on lots from a middle housing land division or in cottage developments) [1][2] |
|---|---|
| Max size | 800 sq ft for a single ADU; 500 sq ft for a second ADU [1] |
| Detached ADU spacing | 6 ft from other dwelling units on the lot (unless both were built before April 1, 2016) [1] |
| Setbacks and height | Set by your zoning district, in addition to the ADU standards [1] |
| Parking | None required; Bend has no minimum parking requirements [5][6] |
| Owner occupancy | Can't be required (state law), except for vacation rentals [6] |
| Fees | Permit fees plus system development charges (SDCs); an SDC deferral program is available [2] |
| Processing time | About 4 to 8 weeks, depending on completeness and your responses [2] |
| Pre-approved plans | Five free plans, 500 to 799 sq ft [2][3] |
| Property tax exemption | None for ADUs currently [2] |
| Short-term rental | Permit required; in the RL, RS, RM and RH zones, only one unit on a property with an ADU can be permitted as a short-term rental [7] |
On this page
What you can build in Bend
Bend's ADU rules are in Bend Development Code 3.6.200(B). "A maximum of two ADUs is allowed per lot or parcel," and ADUs "may only be permitted on a lot or parcel with a single-unit dwelling." The city's ADU Resource Hub describes this as a residential lot with a single-unit home, townhome or manufactured home. An ADU can be attached to your house, part of a converted basement or garage, or a separate cottage in the yard.
Some lots get fewer ADUs. The code doesn't allow ADUs on a lot created by a middle housing land division or in a cottage development, and a small dwelling unit development is limited to one ADU per lot. A second ADU that would push the lot over the zone's maximum density isn't allowed where the sewer main lacks capacity.
Two ADUs per lot became possible with code amendments (Ordinance 2532) that the City Council adopted June 18, 2025, effective July 18, 2025. The city is working on further code updates, so confirm the rules for your lot with the Planning Division. See our Oregon ADU law page for the state rules. [1][2][4]
Size and siting
Size. "A single ADU on a lot or parcel is limited to a maximum floor area of 800 square feet and a second ADU on a lot or parcel is limited to a maximum floor area of 500 square feet." The city's ADU Resource Hub only says ADUs must be 800 square feet or less, but the code sets the 500 square foot limit for a second ADU; confirm with the Planning Division. Floor area is measured inside the exterior walls. Areas with a sloped ceiling lower than 5 feet don't count, and an attached accessory structure that you can't reach from inside the ADU, or that provides a parking space for the ADU, doesn't count either.
Detached ADUs. A detached ADU must be at least 6 feet from other dwelling units on the lot, measured between building footprints, unless each structure was legally built before April 1, 2016. The city's 500 square foot Modern Mill House plan is labeled as qualifying "as a 2nd ADU design."
Setbacks, height and coverage. ADUs must meet the standards of your zoning district in addition to the ADU rules, so setbacks, height and lot coverage depend on your zone. Contact the Planning Division at (541) 388-5580 ext. 3 to confirm the numbers for your lot. [1][2][3]
Parking and owner occupancy
Bend's code says "There are no minimum parking requirements in the City of Bend." Oregon law also says reasonable siting and design rules for ADUs don't include "owner-occupancy requirements of either the primary or accessory structure or requirements to construct additional off-street parking." Cities may still require owner occupancy or parking for ADUs used as vacation rentals. [5][6]
Fees and SDCs
"Fees can vary considerably for ADU Applications." Your cost includes permit fees and system development charges (SDCs), and permit fees depend on the ADU's square footage. Even with a free pre-approved plan, you pay building permit and site-specific plan review fees, SDCs and planning fees.
For a permit fee estimate, which also includes SDC information, email building@bendoregon.gov or call a Building Permit Technician at (541) 388-5580 ext. 2. For SDC amounts or the SDC Deferral Program, contact Development Services at development@bendoregon.gov.
Bend doesn't currently offer an ADU property tax exemption. For other incentives, contact the Housing Department at (541) 323-8550. For budgeting help, see our ADU cost guide and ADU financing guide. [2][3]
Free pre-approved plans
Bend's Pre-Approved Plans Program offers five plans that are free to use for permitting inside city limits:
- Cascade Cottage: 779 square feet, 1 bedroom, single level, Type A accessible
- Modern Mill House: 500 square feet, 1 bedroom, slender footprint, qualifies as a second ADU design
- Deschutes Bungalow: 799 square feet, 2 bedrooms, single level, Type A accessible
- Mt Bachelor Pad: 799 square feet, 2 bedrooms, second-story living over a two-car garage
- The Joel: 576 square foot studio, shared by the City of Eugene
You can't change a pre-approved plan. You still need a site plan, the program's submittal checklist and a signed end user agreement. The Master/Reissue program is limited to sites that don't exceed 2 feet of slope at the footings and don't need design changes. [3]
Garage conversions and existing structures
An ADU can be part of a converted space like a basement or garage. Many backyard sheds and outbuildings were never permitted or inspected as new structures. In Oregon, detached non-habitable accessory structures under 200 square feet don't need structural permits, but an ADU is habitable and does need permits, along with mechanical, electrical and plumbing permits. Email building@bendoregon.gov about converting an existing structure. See our garage conversion guide. [2]
Renting it out
State law lets cities regulate ADUs used as vacation rentals, including requiring owner occupancy or parking for them. Bend's short-term rental rules (BDC 3.6.500) require a permit for each dwelling unit used as a short-term rental. In the RL, RS, RM and RH zones, and in the MR zone outside the Old Mill District, applications submitted after November 4, 2021 for a property with more than one dwelling unit, such as a house and an ADU, "can only have one unit permitted as a short-term rental." Ask the Planning Division at (541) 388-5580 ext. 3 before you plan to list an ADU as a short-term rental. [3][6][7]
Permit steps in Bend
Check your lot
Confirm your zoning, and ask the Planning Division at (541) 388-5580 ext. 3 or planning@bendoregon.gov about setbacks and the number of ADUs your lot allows. [1][3]
Get a design
Use a designer or architect, or choose one of the city's free pre-approved plans. [2][3]
Prepare your documents
Complete the items on the city's Residential Submittal Checklist, linked from the ADU Resource Hub. For a pre-approved plan, add a site plan, the program checklist and the end user agreement. [2][3]
Apply in the city's permit portal
Sign up for a city permit Portal account, choose New Construction/Installation, and upload your documents. One permit covers both Planning and Building Safety review. For a pre-approved plan, mention the Pre-Approved ADU Program in the project description. [2][3]
Answer review comments and pay fees
Processing takes about 4 to 8 weeks, depending on how complete your application is and how fast you respond to plan review questions. Pay permit fees and SDCs, or ask about the SDC Deferral Program. [2]
Build and get inspections
Build to the approved plans and schedule the required inspections. For questions, contact Building Safety at building@bendoregon.gov or (541) 388-5580 ext. 2. [3]
Pre-approved and sample plans
City of Bend Free Pre-Approved Plans Program
Five free plans (Cascade Cottage, Modern Mill House, Deschutes Bungalow, Mt Bachelor Pad and The Joel), 500 to 799 sq ft, licensed for permitting inside Bend city limits. [3]
Who to call
-
Bend Permit Center, Building Safety Division
Permit fee estimates, building code and inspections
(541) 388-5580 ext. 2
City Hall, first floor, 710 N.W. Wall St., Bend, OR 97703
-
Zoning, setbacks and ADU standards
(541) 388-5580 ext. 3
-
System Development Charges (Development Services)
SDC amounts and the SDC Deferral Program
(541) 388-5580 ext. 5
-
Water service questions
(541) 317-3000 ext. 2
Questions people ask
How big can an ADU be in Bend?
Up to 800 square feet for a single ADU, and up to 500 square feet for a second ADU on the same lot. Floor area is measured inside the exterior walls, and low sloped-ceiling areas under 5 feet don't count. [1]
Can I build two ADUs in Bend?
Yes, on most lots with a single-unit home. The code amendments allowing up to two ADUs took effect July 18, 2025. The second ADU can be up to 500 square feet. Lots from a middle housing land division, cottage developments and small dwelling unit developments have lower limits. [1][4]
Are there free ADU plans in Bend?
Yes. The city offers five free pre-approved plans from 500 to 799 square feet. You still pay permit fees, SDCs and planning fees, and you can't change the plans. [3]
How long does an ADU permit take in Bend?
The city estimates 4 to 8 weeks, depending on how complete your application is and how quickly you answer plan review questions. [2]
Sources (7)
- Bend Development Code 3.6.200(B) Accessory Dwelling Unit (code current through Ordinance NS-2558, passed August 5, 2026), City of Bend. Accessed October 9, 2026.
- Accessory Dwelling Unit Resource Hub, City of Bend. Accessed October 9, 2026.
- Pre-Approved Plans Program, City of Bend. Accessed October 9, 2026.
- Development Code and Sign Code Updates, City of Bend. Accessed October 9, 2026.
- Bend Development Code 3.3.300 Vehicle Parking Standards for On-Site Parking, City of Bend. Accessed October 9, 2026.
- ORS 197A.425 Accessory dwelling units, Oregon State Legislature. Accessed October 9, 2026.
- Bend Development Code 3.6.500 Short-Term Rentals, City of Bend. Accessed October 9, 2026.