Building an ADU in Minneapolis

City code and Minnesota law · Last reviewed October 9, 2026

Minneapolis allows one accessory dwelling unit (ADU) on a lot with a single-family or two-family home. It can be inside the house, attached as an addition, or in a separate building such as a unit over a garage. Internal and attached ADUs are capped at 800 square feet; a detached ADU can reach 1,300 square feet or 16% of the lot, up to 1,600 square feet, and 21 feet tall. You need a $325 zoning approval and a building permit. For new ADUs, the owner has to live on the property only with some internal ADUs. [1][2][3]

Minneapolis at a glance
Where ADUs are allowedOn a lot with a permitted or conditional single-family or two-family home [1][3]
How manyOne ADU per zoning lot [1]
TypesInternal, attached or detached (including a unit above a detached garage) [1][4]
Max size, internal and attached800 sq ft (an internal ADU may be larger if that part of the house existed on January 1, 2015) [1]
Max size, detached1,300 sq ft or 16% of the lot, whichever is greater, counting garage space; never over 1,600 sq ft or the size of the house [1]
Minimum size300 sq ft [3]
Detached ADU height21 ft, unless a variance is granted [1]
Detached ADU setbacksInterior side yard at least 3 ft; rear yard can drop to 3 ft; 10 ft from the habitable part of the house [1]
ParkingNo minimum parking requirement [2][3]
Owner occupancyOnly for an internal ADU that is not a separate dwelling unit under the State Building Code: an owner must live on the lot, with a recorded covenant. Not required for new attached or detached ADUs [1][3]
Zoning application fee$325 (administrative ADU review) [2][3]
Selling the ADU separatelyNot allowed as a separate tax parcel [1]
Short-term rentalStays of 30 days or less need a short-term rental license [11]
On this page
  1. At a glance
  2. What you can build here
  3. Size, height and setbacks
  4. Parking
  5. Owner occupancy
  6. Fees
  7. Timeline
  8. Garage conversions and units over garages
  9. Water and sewer
  10. Renting it out and selling
  11. Permit steps
  12. Who to call
  13. Questions people ask

What you can build here

Minneapolis allows internal, attached and detached ADUs "accessory to a principal residential structure." The main building must be a permitted or conditional single-family or two-family home; ADUs are not allowed with any other use. You can have no more than one ADU on a zoning lot.

The city describes the three types this way:

The city defines an ADU as a dwelling unit on the same lot as a home "and that is subordinate in area to the principal dwelling." For what Minnesota state law says, see our Minnesota ADU page. [1][2][3][4]

Size, height and setbacks

Internal ADUs are limited to 800 square feet. They can be bigger only if the part of the house they are in existed on January 1, 2015, and never bigger than the house's first floor. The whole unit must be on one level.

Attached ADUs can have up to 800 square feet of gross floor area, and their main exterior materials must match the house.

Detached ADUs can have up to 1,300 square feet or 16% of the lot area, whichever is greater. That total includes garage space on all levels. In no case can it exceed 1,600 square feet or the gross floor area of the house, whichever is less. The detached ADU, all other detached accessory buildings and any attached parking can cover no more than 800 square feet or 10% of the lot, whichever is greater. Decks, stairs, landings and similar attached structures count toward that footprint.

Other detached ADU rules:

For internal and attached ADUs, new entrances can't face the street, and stairs to an upper-floor unit must be enclosed or entirely at the rear. For all ADUs, balconies can't face an interior side yard. Decks, including rooftop decks, must be at least 5 feet from an interior side property line.

A summary table in the city's ADU application (revised July 2024) lists the 1,600-square-foot cap but leaves out the code's limit tied to the size of the house. Go by the code, and confirm with zoning staff. [1][3]

Parking

You don't need to add parking. The zoning code's parking chapter says the regulations "do not mandate a minimum number of automobile parking spaces." The city's ADU application says there is no minimum or maximum parking requirement for the house or the ADU. [2][3]

Owner occupancy

For new ADUs, owner occupancy applies only to some internal ADUs. If the internal ADU is not a separate dwelling unit under the Minnesota State Building Code, an owner must live in one of the units as their primary residence. Before the permit is issued, you record a covenant with the Hennepin County recorder that runs with the land and tells future buyers about the rule.

New attached and detached ADUs have no owner-occupancy rule. Attached and detached ADUs built before March 6, 2021 under an owner-occupancy covenant stay subject to it. You can ask the city to release it after a building official confirms the ADU meets the state building code for a dwelling unit. [1][3][5]

Fees

Fees are paid when the permit is issued. If you start work before getting a permit, the city may double your fees. See the city's building permit fee schedule for current amounts.

Sewer availability charge (SAC): the Metropolitan Council's 2026 SAC Procedure Manual assigns one SAC unit per dwelling unit, at a 2026 base fee of $2,485. Remodeling or additions that change the number of dwelling units trigger a SAC determination. Ask Minneapolis Development Review whether SAC applies to your ADU.

Plumbing, mechanical and electrical permits are separate; Minnesota's Department of Labor and Industry handles electrical permits. See our ADU cost guide for whole-project budgeting. [2][3][6][7][8][9]

Timeline

The city estimates 15 business days for the initial plan review, and five business days each time you resubmit plans. Zoning staff send a letter within 15 business days if your ADU application is incomplete, and an application left incomplete for 30 days or more is deemed withdrawn. Anyone affected can appeal the zoning decision to the Board of Adjustment within 10 calendar days. See our ADU permit process guide for the general sequence. [3][10]

Garage conversions and units over garages

Minneapolis's building code handout covers detached ADUs, including an addition above a detached garage. Key points:

Garage space counts toward a detached ADU's floor area and footprint limits. See our garage conversion guide. [1][9]

Water and sewer

A detached ADU is usually served by water and sewer lines extended from the main house; dedicated services may be allowed in special circumstances. A licensed master plumber or registered engineer must confirm the existing service can handle both units. Undersized services must be replaced, and a lead water service must be replaced in full before it is extended to an ADU.

If the ADU is served through the house, the city supplies and reads a single water meter in the house; submetering is up to you. An ADU with its own line gets its own city meter. [9]

Renting it out and selling

If you charge rent for a stay of 30 days or less, you need a short-term rental license. An owner can have only one short-term rental property besides their home, and occupancy is limited to 10. Rentals of more than 30 days need a regular rental license instead.

Creating an ADU "shall not create a separate tax parcel," so you can't split it off and sell it separately from the main house. [1][11]

Permit steps in Minneapolis

  1. Check your zoning

    Look up your property on Minneapolis Property Info or call 311 at 612-673-3000. ADUs are allowed only on lots with a single-family or two-family home, and only one per lot. [1][3]

  2. Talk to zoning and plan review staff

    The city encourages you to meet with Zoning and Plan Review staff before you apply to go over the zoning rules and building codes for your design. [3]

  3. Prepare your plans

    You need a scaled and dimensioned site plan, elevations of each side, floor plans for every floor, and photos of the property. The site plan must be prepared by a Minnesota-licensed architect, landscape architect, engineer or land surveyor, though the zoning administrator may waive this when no new principal building is involved. Plans must meet the 2020 Minnesota Residential Code. [3][9]

  4. Apply for a building permit

    Submit a building permit application. A development coordinator starts your permit and emails you an invitation to upload plans in ProjectDox. [10]

  5. File the ADU land use application

    ADUs need an administrative zoning application ($325), and zoning staff will contact you about it. Download the ADU application packet. Incomplete applications get a letter within 15 business days, and the zoning administrator's decision can be appealed within 10 calendar days. [3][5][10]

  6. Record the owner-occupancy covenant (internal ADUs only)

    For an internal ADU, record the city's covenant for owner occupancy with the Hennepin County recorder and give the city proof before the building permit is issued. [1][3][5]

  7. Get plan approval and pay for the permit

    The city estimates 15 business days for the first plan review and five business days for each resubmittal. When all departments approve, you pay the fees, download the permit and approved plans, and post them on site. [10]

  8. Pass inspections and get a Certificate of Occupancy

    You schedule inspections as you build, and every project needs a final inspection. A certificate of occupancy inspection is required before a new building can be occupied. [10]

Who to call

Questions people ask

How big can an ADU be in Minneapolis?

Internal and attached ADUs are limited to 800 square feet. A detached ADU can be 1,300 square feet or 16% of the lot, whichever is greater, including any garage space, but never more than 1,600 square feet or the size of the main house. [1]

Do I have to live on the property to build an ADU in Minneapolis?

Only for an internal ADU that is not a separate dwelling unit under the state building code. In that case an owner must live in one of the units and record a covenant with Hennepin County. New attached and detached ADUs have no owner-occupancy rule. [1][3]

Can I build two ADUs on my lot in Minneapolis?

No. The zoning code allows no more than one ADU on a zoning lot, and only with a single-family or two-family home. [1]

Do I need a parking space for an ADU in Minneapolis?

No. Minneapolis's zoning code does not require a minimum number of parking spaces, and the city's ADU application says there is no parking requirement for the house or the ADU. [2][3]

Can I Airbnb my ADU in Minneapolis?

Stays of 30 days or less need a short-term rental license, and an owner can have only one short-term rental property besides their home. Longer rentals need a regular rental license. [11]

Sources (11)
  1. Minneapolis Code of Ordinances, Chapter 550, Article IX: Accessory Dwelling Unit Standards (550.1400-550.1460), City of Minneapolis (Municode). Accessed October 9, 2026.
  2. Minneapolis Code of Ordinances, Title 20: Zoning Code (sections 525.230, 555.10 and 565 definitions), City of Minneapolis (Municode). Accessed October 9, 2026.
  3. Accessory Dwelling Unit Application (revised July 2024), City of Minneapolis, Community Planning and Economic Development. Accessed October 9, 2026.
  4. Accessory dwelling units (building requirements), City of Minneapolis. Accessed October 9, 2026.
  5. Accessory dwelling unit (land use application), City of Minneapolis. Accessed October 9, 2026.
  6. Building permit fees (Minneapolis Building Permit Fee Schedule), City of Minneapolis. Accessed October 9, 2026.
  7. Construction permit fees, City of Minneapolis. Accessed October 9, 2026.
  8. Sewer Availability Charge Procedure Manual (issued January 1, 2026), Metropolitan Council. Accessed October 9, 2026.
  9. Detached accessory dwelling unit: key minimum code requirements (last updated December 10, 2024), City of Minneapolis. Accessed October 9, 2026.
  10. Construction permit application process, City of Minneapolis. Accessed October 9, 2026.
  11. Short-term rental licenses, City of Minneapolis. Accessed October 9, 2026.